You are asked to create a dashboard to meet these requirements:
Which combination of gadgets should you use?
There is a condition on the Start Progress transition in your workflow, which restricts the transition to users in the Developers role only.
All other transitions are available to all users.
There is a new requirement to allow all users to execute the Start Progress transition.
Your workflow is not shared.
As a project administrator, what should you do to meet the requirement?
When creating a project from a template, which two schemes will be unique for the new project? (Choose two.)
You are the project administrator for a Software Scrum Project.
Time Tracking is globally enabled.
Identify the reason why users are NOT able to log work.
Users typically forget to add components when they create new issues. As a result, most of the newly created issues get assigned to Tom, who is the project lead.
Tom reviews all of the issues, and wants to triage them based on component selection. But when he edits an issue and adds a component, the assignee does not change.
Why does the assignee not change when adding a component to an issue?
Max and Emma both have Jira Software application access, and they are members of the same groups and project roles in the DEV project.
However, Max can rank issues on the project's Kanban board, while Emma cannot.
Which configuration will definitely explain the observed behavior?
Fixing a single bug requires the involvement of three teams: Designers, Developers and Testers.
Currently, all the fields that are needed by each of the three teams are together on a single project screen. As a project administrator, how can you help the teams to easily identify the fields they need?
All projects use a simplified workflow which has three statuses (Open, In Progress, Closed) and all global transitions.
You need to find issues which were never In Progress.
Select the correct JQL query.
You are asked to change who receives notifications when issues are moved.
The settings in the default notification scheme used by your project are shown in the table below.
As a project administrator, why are you NOT able to update the notification scheme?
You want to gather metrics on how long it takes the team to resolve issues in their project. Which report should you use?
You want a built-in report that meets these requirements:
Which report should you use?
You work for an insurance company and want to use Jira for tracking customers and their contracts. Before requesting a new project you have gathered some requirements:
How should contracts be configured?
The support team has a request.
When a Bug is created, it should only display five fields. However, when it is edited, it should display fourteen fields.
Which configuration is used to implement this requirement?
You Update the My Changes setting in your user profile to Do not notify me.
Which statement is true?
In my project, I can create issues and assign them to other users. However, the other users are not able to assign issues to me.
What are two possible reasons for this? (Choose two.)
Teresa is able to see the Start Progress transition but not the Approve transition on an issue. Her co-worker is able to see both.
Identify two possible causes why Teresa can NOT see the Approve transition. (Choose two.)