A project manager is appointed for the deployment of a new solution. The solution will be integrated into the environment by a third-party vendor. This vendor just announced a delay in delivering a key component, which will impact the project schedule.
What should the project manager do?
In the middle of the execution phase for a big project a new stakeholder who was unfamiliar with the project joined the board of directors and is influencing the decisions made in the project. This change is impacting the project's progress
What should the project manager do first?
A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.
What should the project manager do?
During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.
What should the project manager do?
A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce
the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on 20 December
might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.
What should the project manager do about this risk?
A project manager is transferred to another country to perform a project within their organization. What should the project manager do first to ensure collaboration within the team for a successful delivery?
During the execution stage, the project manager discovered that one team member is not able to complete their work on time and is running later than expected. This delay may potentially impact a project milestone.
What should the project manager do first?
A project manager is working on a project with three virtual teams. Team A is in a different time zone than teams B and C. The project was going
well, but recently team A has started feeling left out. Information reaches team A late or is sometimes missed, and teams B and C give preference
to each other's problems over team A. The project manager has already set project guidelines, but realizes they need to be improved.
Which two things should the project manager do to help the teams collaborate better? (Choose two)
A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely Some team members returned to their hometowns and they are now requesting reimbursement for operational expenditures
What should the project manager do?
A functional manager is concerned that the project's quality management techniques have advanced beyond the department's capabilities and wants the project team to review all quality management activities in two full-day workshops the following week. What should the project manager do next?
A team member is hosting an event and invites several colleagues through their work calendars Another team member, who was not invited to the event, is noticeably distracted during several standup meetings
What should the project manager do?
A team is working on a project using a hybrid approach, and they are facing a lot of obstacles and blockers from some stakeholders. What should the project manager do to improve project performance?
A team shared a complaint regarding the scrum master during the last sprint review. The team expressed that they were delayed because the
scrum master did not remove impediments, such as scheduling some meetings with external teams and obtaining a room to work collaboratively,
among other critical blockers.
What should the project manager do?
A project manager is working on a multinational project that has more than 100 stakeholders. The project manager is concerned about the
appropriate stakeholder participation and involvement level required for successful project delivery.
What should the project manager do?
A project manager has been assigned to deliver a challenging project on time and within budget. The project manager needs to empower the team members by removing organizational impediments and facilitating collaboration.
What should the project manager do to lead the project?
Due to a statewide emergency, a project team for a global insurance company is being forced to complete a project virtually, The project manager is tasked with conducting meetings where confidential patient information will be presented.
What tool should the project manager use to conduct meetings with the project team and clients?
While preparing an earned value analysis (EVA) for the sponsor, the project manager provided this information in the latest project report:
What is accurate about the project status?
During project implementation, one team finds out that a key project deliverable was not budgeted. What should the project manager do first?
A project manager has been assigned to a long-term project. The project manager came across a government debate over a new law that may affect the project.
What are the first two actions the project manager should perform? (Choose two)
When defining the ground rules for a project team, the project manager observed that only two team members contributed to the discussion. As a
result, the team ground rules favor these two team members.
What should the project manager have done to avoid this situation?
A project has met the agreed-upon product requirements and is closing. There is time remaining in the schedule and excess budget. The
resources are not yet scheduled to move to other projects. Several product champions want to continue adding functionality to the product.
What should the project manager do?
A project manager has been assigned a low-priority project that includes new team members with no previous formal project experience. The project team has requested deadline extensions for the first development increment twice already.
What should the project manager do to support the team?
A lead project manager for an agile project needs to prioritize requirements define the scope of the initial product and deliver the approved scope in a series of multiple versions. What should the project manager do next?
An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase
What should the team do next?
A project manager must manage a virtual application control software team that is culturally and geographically diverse. The project manager wants to promote open collaboration in a Realtime manner.
What should the project manager do?
The operations director complains to the CEO about the outcome of a project's first sprint The operations department will not be able to support a new product due to poor performance indicators The project team facilitator asks for feedback from the project team and is informed that performance information is available in the application server log
How should this complaint be addressed?
A project sponsor insists that the project scope for a new product launch should include two geographical locations. However, after the project scoping session was done, a project charter was completed and approved with one location only.
What should the project manager do?
A project manager is assigned to a global project where, during the planning process, team members from different regions are not agreeing to collaborate with each other What should the project manager do?
The product team is progressing with a prototyping approach to deliver a multiyear business initiative A few user stones are taking longer to be delivered.
What should the project manager do?
A project team consisting of various professionals of different nationalities is struggling to achieve their project deliverables. What should the
project manager do?
A project manager recently joined the company. At the interview, the project manager demonstrated experience with agile delivery, and the project management office (PMO) manager asked for assistance in implementing agile.
What should the project manager do to initiate the adoption of agile within the company?
A project manager is implementing an enterprise-wide software project The project has a great business impact and is fully supported by senior management However, the project manager is facing difficulties gelling the support of several key departments.
What should the project manager do?
A self-organizing team for a critical project is consistently delivering value according to their commitments. During a retrospective, the project manager observed that most of
the team members were stressed due to over commitments.
What should the project manager do?
A scrum team's daily meetings are conducted by teleconference between three teams, each located in different countries. The meetings typically
last 45 minutes with many misunderstandings due to language barriers.
How should the project manager resolve this issue for the next iteration?
A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the
system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the
year. The project team is concerned that one of those tickets could be the winner.
What should the project manager do first?
During the execution phase, the project manager discovered that the deliverables
are not meeting the quality specifications requested by the main stakeholder. This has
caused the schedule performance index (SPI) to deteriorate from 0.98 to 0.72 and the cost
performance index (CPI) from 1.5 to 1.1.
What action should the project manager take to mitigate the issue of the deliverables being
rejected during the next iteration?
A project manager is working on a construction project. The company owner asks the project manager to provide cost estimates for the new decoration project within 4 hours.
How will the project manager be able to complete this task?
A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,
What should the project manager, as a servant leader, do to address this situation?
A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the
importance of the project meeting the company's strategy, investment, and compliance requirements.
What should the project manager do?
A laboratory is launching a new product, defined to be executed in eight iterations with a fixed release date. At the beginning of the second
iteration, the project manager realizes that a significant regulatory feature is missing in the project backlog.
What should the project manager do?
A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule.
What should be me project manager's response?
A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.
How should the project teams interact in their meetings?
A project manager is assigned to a time-bound internal project on quality improvement During project execution the project manager observes that a specific team member is being isolated by other team members
Which three actions should the project manager take? (Choose three)
During project execution, a global project team was using a video conferencing tool to support the daily meetings. However, during these meetings, only a few team members were actively participating As a result lots of misunderstandings occurred
What should the project manager do to address this issue?
A sponsor and project manager found out that a vendor in a different time zone has delayed the delivery of its products and needs close supervision until the project gets back on track. The only option is to relocate three key members of the project team to spend 6 months abroad
What should the project manager do next?
An agile project has a documented list or requirements prioritized in high, medium, and low categories. The project team has expressed that it is difficult to know what to work on next as so many items are listed as high priority.
What should the project manager recommend?
After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?
A project manager is leading a cross-organizational project that is replacing a platform on which various solutions used by 15 business units were built. The project is part of a large program of work, and some of the resources are shared with other projects outside of the program initiated by the respective business units.
Which stakeholders should the project manager consult with first to manage interdependencies?
A verbal announcement is made that the new team member joining the Scrum team has limited mobility The scrum master is aware that some team members are unsure how the dynamics of the team will change
What should the scrum master do?
During the execution phase of a large project there is an extremely high number of change requests Because of this the project manager realizes that there is a greater risk for rejection of the deliverables
How should the project manager mitigate this risk without compromising the completion date?
During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)
A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.
What should the project manager have done to prevent this?
A project manager is managing a project that is going to deliver a new risk platform. This platform will enable data-driven and new risk market models to ensure compliance with new regulations. The regulatory requirements for the models are released continuously and are not fully fixed yet. The project manager is reviewing the risk register and added a few new
Hems
Match the risks on the left lo the correct category on the right.
A project manager for a large software delivery project is in the process of finalizing the project governance, The project manager would like to implement procedures that do not align with several policies required by the organization's project management office (PMO). The project manager
believes that the procedures outlined in the project governance will be necessary for this particular project due to the unique nature of the
technology.
What should the project manager do?
A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
A large company has agreed on a business case for an environmental project. The
project will cause some major changes in their operations, such as reduction in paper use,
which will obviously affect all of the users.
What is the first thing the appointed project manager should do?
During the execution of a project within an operations function the project manager encounters scope changes and a delay in the delivery of critical tasks How should the project manager address this situation?
During the execution phase of a project, a new department has been created in the company. The manager of this department has requested to
be involved in the regular project communications and reporting cycles.
What should the project manager do?
A project manager has been assigned to lead a software project to generate savings at an important financial institution. Initially, the duration of the project was 13 months,
but due to various issues during execution, the project was extended to 16 months. By month 11, the expected savings were exceeded but not all of the functionalities
planned for that date were fulfilled.
How should the project manager inform the stakeholders of the project's progress?
A project manager in a matrix organization has been assigned to a system solution project with tight time lines. There are two resources assigned as part of the solution
team: one who is experienced and one who is new. During development, the project manager notices that the resources disagree on the solution approach.
What should the project manager do next to deliver a reliable solution?
A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?
In a geographically distributed team, a developer continues to delay a coding activity. This activity is on the critical path. The project manager
found out that the delay is due to the developer's lack of understanding of the customer requirements shared by the off-site team.
What should the project manager do?
After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.
What should the project manager do?
A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility,
Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.
What should the project manager do next?
A project is coming to a close, and the experienced project team members will be moving on to the next project. Who is responsible for ensuring that the appropriate knowledge transfer is done prior to project closure?
A project manager has just completed a fixed-price project and the stakeholder is unhappy with the result What should the project manager do?
An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.
An agile team completes a deliverable that is to be certified by another expert team The second team does not take the deliverable for many months What should the servant leader do?
A project engineer in country A is complaining about the sample received from the supplier in country B because the sample is not the correct length. During a telephone conference, the supplier checked the drawings and insisted that the measurement was accurate.
What should the project manager do next?
A large corporation is transforming itself from a predictive to agile approach A project team with knowledge of agile practices is experiencing significant conflicts with the executives regarding the processes to be followed.
How should these conflicts be resolved?
A contractor delivering construction services to a company is using agile principles
to manage the project tasks. Engineers are producing frequent design changes due to new legislation. There is a risk the contractor may lose money due to resources waiting on design
changes or performing rework.
What should the project manager do to minimize the cost?
An operations manager continuously raises concerns about a project's benefits to the company While some concerns are valid most of the time these concerns have caused delays in project meetings
How should the project manager handle this'?
A project manager is assigned to an important company project. While reviewing the lessons learned from a similar, previous project, the project manager finds that the biggest challenges were related to learn motivation.
What should the project manager do to avoid these challenges?
A protect manager is managing a project that will handle sensitive data for millions of users The sponsor mentioned that, lo their knowledge, the project does not seem to have any compliance requirements in their country.
What should the project manager do in this situation?
A senior business stakeholder with many years of experience is pressuring an agile team to deliver most of the promised functionality to the customer 18 months in the future as opposed to multiple, incremental deliveries over the course of the 18 months What should the project lead do next?
How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?
A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict
schedule and budget, and the project manager is concerned about their ability to deliver it.
What should the project manager do?
In an effort to modernize the technology for a project, the project manager has been discussing risk prioritization with the project team. The project manager determines that additional parameters are needed to iteratively assess and prioritize the project risks.
Match the project manager's goals on the left with the relevant risk parameter on the right.
Two members of a new project team disagree on the best approach to solve a problem. The conflict has been going on for 1 week. The two
members are tense around each other and are taking everything personally.
What should the project manager do?
A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.
What should the project manager do next?
Midway through the execution of an agile project, there is a shift in the strategic objectives at the organization level to promote digital transformation. What should the project manager do next?
A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.
What should the project manager do to support the backlog prioritization?
A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government
official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include
aspects that the previous project sponsor did not support.
What should the project manager do next?
A project team has expressed concern that certain remote team members are not able to collaborate with the larger project team due to their work schedule. The project
manager is confused since the entire team is located in the same time zone and believes there are other factors at play.
What should the project manager do next?
A project manager has received feedback from stakeholders regarding poor communication about project progress. Weekly status reports were provided to the project management office (PMO), and the standard communications management plan was followed.
What should the project manager do?
In an agile environment, a project is running iteration four out of six. A team member leaves the company with no replacement.
What should the project manager do?
A project manager is working on an agile project in a changing business environment. The project sponsor is worried about benefits realization
and asks the project manager to pay attention to changes that can affect the project.
Which action should the project manager take to identify changes that may affect the product?
A project team is planning the next sprint review. The project lead receives an email from a senior manager asking for a project status using a template that is more detailed than the one used for monthly reports sent to the project management office (PMO). The team uses an electronic product backlog and a kanban board to track the progress.
What should the project manager do next?
A project manager is assigned to work on a complex and innovative project. The technology being used and developed is new and complicated, and most of the stakeholders are unfamiliar with it.
Which approach should the project manager use as a servant leader?
An important national project is in (he execution phase. A time constraint activity must be conducted on-site by a specialist from another country. Due to travel restrictions, the specialist cannot perform the activity on-site. The activity cannot be completed without the specialist's expertise. The project team is actively seeking assistance in order to complete the job on time.
What should the project manager do to help the project team?
A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team?
A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.
What should be used to prioritize the backlog items?
A project team is performing a post-release evaluation of a product that requires detailed feedback from seven stakeholders. Six of the stakeholders have promptly provided feedback. One of them has not provided any feedback despite numerous requests from the team.
What should the project manager do in this situation?
An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.
What should the project manager do?
A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After
discussing these concerns with the team, it is determined that the project does not have the full support of senior management.
What should the new project manager do next?
A project manager assigned team members to work in pairs on a large amount of technical reports. At times, the project manager noticed that important information was not
shared properly among the team. This has caused delivery delays and, ultimately, the failure to complete the project.
What is the root cause of this issue?
A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.
How should the project manager build a cohesive, high-performing team?
A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.
One particular pain point is the transition to operations, where the issues usually arise.
What should the project manager do to improve this scenario?
A project team is engaging a development team in another country to develop software. During progress reviews, the project manager identified completion date delays due to rework because there were different interpretations of the client's needs.
What should the project manager do?
A company plans to initiate a project involving a new technology. Approval for the project is required. What should the project manager do?
A high-tech borehole protect was initiated with the goal of providing water for a rural community of 1500 villagers located in an arid region. The project was completed with a cost performance index (CPi) of 1 09 and a schedule performance index (SPl) of 0.93 Six months after its completion it is determined that the villagers could not access water
What caused this situation to occur?
A project manager is evaluating a project and realizes that its earned value (EV) shows the cost spent is higher than the value delivered. The project manager then discovers that the team has been adding small features that are not part of the requirements.
What should the project manager do?
The project team is planning a schedule with limited information. The team |s having
issues identifying the detailed tasks and estimating task durations.
Which three techniques should the project manager use? (Choose three)
An agile coach and technical writer for a globally distributed agile team are In a country with a 9-hour time zone difference from the agile team. The agile coach and project lead disagree on the timing for the daily standup. The project lead thinks the standup should be at 10:00 am local time, but
the agile coach and technical writer feel that is an inconvenient time for them.
How does the project lead ensure adherence to agile practices?
During the closing process, the project manager learns that one deliverable is not meeting customer expectations How should the project manager proceed?
A project manager for a technology project is informed by the cybersecurity team that
there are changes in the government's cybersecurity requirements. The project manager calls a team meeting to discuss the requirements, and the team learns that the design changes can be made at no additional cost.
What should the project manager direct the team to do?
One of the key stakeholders on the project team reaches out with an additional requirement that may impact the overall schedule. A discussion with another stakeholder suggests thai this might just be a small task.
What should the project manager do?
During the implementation phase of a project, functional managers are adding new requirements, which may impact cost and schedule baselines. The project manager
notices that some of the team members are communicating with their managers directly to fulfill their requests. This will lead the project to go beyond the agreed baselines.
How should the project manager handle this situation?
A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and
delay new feature development.
Which action should the project manager take to resolve the quality issues?
A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix
What should the project manager do with regard to community engagement in this situation''
A project manager /s planning a project and identifies that legislation requirements for specific project tasks will be changing. This will occur half way through the project execution
phase and will affect a few key workers’ licenses, which will become noncompliant.
What should the project manager do?
As a result of the first iteration review, the stakeholders' feedback indicated that they saw more technical features than business ones What should the project manager do?
A new team member is hired and the training is taking longer than expected. This impacts the overall project performance.
What immediate action should the project manager take to improve the situation?
In an attempt to streamline project communications, a project manager established a shared portal for all stakeholders to get project information. The sponsor complained about this system and says that it is ineffective.
What should the project manager have done to prevent this situation from occurring?
A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team
members and stakeholders who have contradictory opinions.
What should the project manager do?
A project is scheduled to end in 2 weeks. The team is expected to continue working long hours and is showing signs of weariness and fatigue What should the project manager do to encourage the team?
A project manager is closing a project and preparing to hand it over to the operations team. During handover, a delayed invoice was submitted with a higher-than-planned
cost against the project work. Consequently, project handover was delayed and the project's reported completion costs were increased.
What should the project manager have done to avoid this situation?
A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.
What should the senior project manager do now?
A project manager was informed by their supplier that there will be an upcoming raw material shortage due to a regulatory change. What should the project manager do?
In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner. What should the project
manager do next?
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will
take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6
months.
What should the project manager do to align stakeholders’ needs and expectations?
A project manager is managing an internal software development project that is on schedule to complete in 1 month. The project should begin seeing value once the system is online,
yet some stakeholders lack an understanding of how it will provide value to the organization.
What should the project manager do next?
During an iteration review session, some product features are at risk of being canceled due to high operational costs when the product is launched into a production environment. What type of analysis should the project lead have conducted to avoid this situation?
A company is going through structural changes. A couple of people will leave the company as their positions were made redundant. The team members are unhappy as they do not understand why the changes are being made when the project is on track.
What should the project manager do?
After a recent status review meeting, the project manager becomes aware that an influential stakeholder is unclear about the purpose and benefits of the project Consequently, the stakeholder has questioned the viability of continuing the project What should the project manager do next to address the situation?
A project being constructed in a remote rural area is nearing the end of construction. The project manager would like to share the good news with stakeholders.
How should the project manager communicate with the local community?
A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.
What should the project manager do?
A project manager is part of a distributed team. The project team is using a product backlog, but due to an excessive workload, the backlog items are not very detailed. In the retrospective, a couple of new team members are raising the issue of knowledge transfer inside the team.
What should the project manager do?
A company has created a cross-functional team to drive the digital transformation project for the business. The team is expected to deliver the minimum viable product (MVP) that addresses market need in the shortest possible time.
Match the roles for the team on the left to their corresponding responsibilities on the right.
A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.
What should the project manager do first?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?
A geographically distributed project team working on an iterative project adopts a new mode of communication following changes in health protocols. The colocated team members are finding themselves challenged with understanding verbal communication and collaboration methods.
What should the project manager do?
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to
outline situations, solutions, results, and suggestions.
How should the project manager use the information collected?
An agile team wants to maximize the work delivered for the upcoming project that involves considerable product complexity. What should the
project manager do to help improve the team's collaboration approach?
A project manager has been assigned to manage multiple agile project teams. The project manager wants to empower the teams and make them self-organizing.
What should the project manager do to create a positive environment?
A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?
A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
A project needs to be outlined as a phased approach for multiple product lines with a review gate at the end of each phase. To ensure consistency for this hybrid delivery, what should the project manager do?
A project in aerospace design has run into a substantial technical issue, and the project team is uncertain on how to proceed. With whom should the project manager call a meeting to discuss the issue?
A project manager finds that team members In an agile project are involved in several different projects due to budget constraints. What should the project manager do?
A project manager joins a startup and discovers that the chief technology officer (CTO) encourages the team to overlook some procedures in the interest of speed. What should the project manager do to ensure that all the procedures are followed in the future?
A product owner has an idea for a new product but is struggling to define the
features because they are not certain of the perceived business value for each feature. What should the project manager have the delivery team do to address this issue?
During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past
What should the project manager do next to improve this situation?
A project manager receives a request for proposal (RFP) from a client. The client
is very clear about the requirements. A requirements analysis must be done in the first
month of the project, and the client wants to see a demo of the work completed every two
weeks.
What project approach should the project manager use?
The project manager of a large construction project discovers that the blueprints received from the client appear incomplete. What should the project manager do first?
During a project status update by the project management office (PMO), the CEO is concerned that the status of all projects suddenly changed from green to red, without warning. Upper management is used to reading traditional reports related to progress and cost, and they want to continue viewing this information.
How should the PMO implement a better way to report the project's health?
An agile project is running its second of six iterations. One new team member who does not have agile experience has just joined the team. In the daily meetings, the project manager observes that the team is having problems meeting their goals.
What should the project manager do?
The portfolio management office wants to cut costs by suspending some ongoing
projects that do not directly support the organizational strategy. The project manager has invested too many resources into one of the projects to be suspended, but the portfolio
management office has not backed down on their plan.
What should the project manager do to continue the project?
A project manager is managing a project aimed at providing incremental deliveries to the market every three months. The team has been assigned, and the product backlog was created and prioritized by the product owner. After four iterations, the product owner escalates complaints to the CEO because the product does not meet the product owner's expectations.
What should the project manager have done to prevent this situation from happening?
A project that is using an incremental approach has colocated team members and is using a kanban board to visualize the work in progress
(WIP). A key external stakeholder requests that all project activities be placed on hold until a status report is distributed.
What should the project manager have done to avoid this situation?
A team needs to implement a mandatory compliance regulation in a product, which is required for its release. While nearing the product release, when completeness was
being verified, it was found that the compliance part was not implemented in the project.
What should the project manager do next?
An organization embarking on a significant transformation initiated a project to improve and document business processes. One of the objectives of the project is to implement agile project delivery.
What is the main reason for adopting agile?
A project manager is assigned to a new project. The project is for a new product that the company wants to launch as soon as possible to test market readiness. The project is part of a large business transformation, and the objective is to open delivery channels for the new product.
Which delivery approach should the project manager recommend?
A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.
Which estimation technique should the project manager implement in this context?
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?
A project manager is leading a software development project that will assist in maintenance management for a power plant. The project manager is analyzing project performance data and trying to forecast if the project will have any slippage in the future.
What should the protect manager do?
A project manager is scheduled to meet with a client for their weekly risk management meeting. The project manager observed that one of the tasks which had external dependencies is delayed by one week. The project manager knows this will have an impact but does not know the exact details.
What two things should the project manager do? (Choose two)
A project team is working on the design of a solution for a complex project. Due to a lack of clarity of the customer's requirements, daily meetings
were agreed upon between the team and the customer. There are a few external contractors in the project who do not agree with this idea as they
feel it is a waste of time.
What should the project manager do?
A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.
What should the project manager review during the management review to ensure the meeting is effective?
A critical project milestone was missed because one of the team members did not complete their tasks on time. This resulted in a heated discussion during a demonstration for the end users.
What should the project manager do next?
A project manager received a request to add features and functions to the project after the scope had already been established. What should the project manager do?
When trying to track project benefits, a project manager realizes that some key performance indicators (KPIs) are not yet defined. What should the project manager do?
A high-performing team is involved in a project with a new domain. The team is unable to deliver as expected.
What should the project manager do?
A team is preparing the closing phase and building a plan for the next phase. One of the project sponsors is complaining that the last phase had some quality deliverable issues. However, the quality acceptance document was signed.
What should the project manager do?
A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.
What should the project manager use to explain the project scope?
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
A project manager is working on a financial system implementation project for a government company. One of the key stakeholders, who uses
predictive approaches, does not like virtual tools such as chats, task trackers, and so forth. They prefer email, telephone calls, and face-to-face
meetings.
How should the project manager approach this situation?
A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them. There are a few complex backlog items, and a new junior tester has identified a few compliance defects. The product owner and a couple of developers will be leaving the project team, and the contract with the test and production support partner will not be renewed.
Which issue should the project lead focus on first?
A company has started developing a new product. During execution the project team notices that another competitor has launched a product with
very similar functionalities and a cheaper market price.
What should have been done differently to avoid this scenario?
A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.
What should the project manager do?
Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?
An agile team is in the early phases of the development cycle for a project; however, they have already begun to deliver functionality to the customer. The team has identified risks to the project and are working on developing the mitigation strategy.
What should the project manager do next?
A distributed project team has communication issues because of their collaboration tools. The team feels that efficiency could be improved by changing the collaboration platform.
What should the project manager do?
An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.
How can the project manager ensure that the appropriate acceptance criteria are applied to the features?
A project manager manages a bridge construction project. The project manager has received a major change request from a regulatory stakeholder to add one branch of the bridge to the engineering design. The project manager prepared a change request, which was reviewed and accepted by the change control board (CCB).
What should the project manager do now?
Anew major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings. Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its
competitors. A new project manager has been hired to change this scenario.
What approach should the project manager propose?
A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?
A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting
What should the project manager have done to avoid this situation?
In a software development project, the product owner and development team agree on a sprint backlog The highest priority in the backlog is to build a payment module The team worked on the module during the first half of the sprint, but now two developers want to spend the rest of the sprint focusing on refactoring another feature that might create issues in the future.
What should the project manager do?
The resource management plan is already done, and the team is located in different countries around the world Team members are in multiple time zones and they use different languages for communication The project manager needs to keep the team organized and avoid misunderstandings and miscommunication that may produce a negative impact to the project
What should the project manager do to reduce negative impacts to the project?
During a daily standup meeting, a roadblock was raised that is preventing one of the team members from proceeding with work The project manager figures out that it is due to a technical issue.
What should the project manager do to prioritize this critical impediment?
During the execution phase of a healthcare IT project, stakeholders made a change request regarding user requirements There is no remaining budget available to cover that change request.
What should the project manager do next?
A member of the board of directors is the sponsor of a project that is important to the organization This stakeholder has many other priorities and is not currently engaged in the project activities
How should the stakeholder be engaged in the project?
During a retrospective review, many project team members say they are not completing tasks during the iterations because of interruptions and requests for help from other teams As a team facilitator, what should the project manager do to avoid this?
A new agile team is forming and the project manager notices that the team is struggling in many areas The team is experiencing both the inability to meet iteration commitments and team member conflicts
What should the project manager do next?
The project is delayed due to the high amount of major changes requested by different stakeholders at different stages of the project If the project continues on the same path, it will consume twice the time and budget planned.
What two actions can the project manager take to be more cost effective? (Choose two)
A project manager is assigned to lead a newly formed agile team. The functional manager has assigned tasks to team members, but the team members do not feel empowered.
How can the project manager promote empowerment and accountability among the team?
A company is initiating a project to enhance one of its existing products. All of its products are developed internally What should the project manager do?
A company is changing their current business model The change requires implementing a complex project using multiple agile teams.
What three options should the project manager have the testing team adopt as testing mechanisms? (Choose three)
A project manager is struggling to figure out the performance of the project teams in an agile environment for the same scope of work, team A has calculated 100 story points and team B has calculated 125 story points
Which team is performing better?
During the review of a project's list of deliverables, one of the stakeholders expressed concern that one of the requirements will not be addressed. What should the project manager do?
An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?
A project manager has been assigned to a project and receives the project charter from the project management office (PMO) The document is very clear about customer requests During Project Scope Management some requirements seem to be different from the ones specified within the project charter
What should the project manager do?
A project manager and project team have brought a project back on track after mapping and removing impediments During the current sprint the team reported that an impediment that previously caused major delays has appeared again. The team tried implementing the same mitigation tasks that worked previously However, the tasks are not having the same result with the impediment
What should the project manager do?
An agile project is in its early iterations, but the project manager already realizes that
more resources will be needed to achieve the expected time lines. There are no internal
resources. available.
What vendor strategy should the project manager use to maximize project delivery?
What is the correct way to put an organization on the proper path to changing their mindset to an agile approach?
A project has issues arising where the data integration team and the data migration team have areas that overlap It is not clear who would be responsible for delivery on these areas What should the project manager do next?
A project manager is part of a team that is launching a series of features to comply with a new regulation. The team has only 6 weeks to release the features to the legacy applications. During the standup meeting, a software engineer indicated that the development of an important feature is
on hold until the assigned designer completes a specific task. This delay is a serious road block to meeting the release date.
What should the project manager do?
As the project progresses, the learns not performing at acceptable levels and in accordance with the key performance indicators (KPls) that were set at the beginning of the
project. How should the project manager resolve this?
A project manager is working on a project to modernize the information technology of a bank, The project manager is facing challenges with the project sponsor regarding how to proceed with implementation of a key piece of technology.
How should the project manager resolve this conflict?
Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?
A project manager for a construction site realizes the importance of stakeholder
relations, especially with the local community. The project manager and the project team strive to build effective relationships with these key stakeholders in order to prevent obstacles in the future.
What should the project manager do to customize the stakeholder engagement plan?
A protect manager is assigned to lead a global implementation of a cloud-based system Team members are dispersed in five countries As time goes on. the project manager notices that some team members have become quiet during status calls or other protect discussions while others often call into meetings late and use time zone differences as the reason for the delay
Which three actions should the project manager take to encourage engagement? (Choose three)
A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?
A senior developer working on a large artificial intelligence (Al) project has worked hard and shown excellent results. The project manager is very happy with the developer's contribution and thinks that the developer deserves a reward.
What should the project manager do?
In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?
A project sponsor asks the project team to add an enhancement to the project How should the project manager address this request?
Match the project situation on the left to the meeting on the right where the situation could occur.
A project manager is managing a project which is approaching the end of the execution phase. A high-level stakeholder informs the project manager that a very important requirement was not included in the scope of the project, and that without that requirement the project will deliver no value.
What is the first thing the project manager should do"?
A new relevant project stakeholder suggested a change to some of the project parameters midway through execution What should the project manager do next?
During a project review meeting, the project sponsor is worried that the protect may not be delivering results as planned Based on that the project manager is evaluating the project status. What information should the project manager use as an indicator that the project is actually delivering value?
A business stakeholder for a project is reluctant to accept an agile approach due to a previous bad experience, and is pushing for a predictive approach. What strategy should the project manager use to persuade the stakeholder to use an agile approach?
A project manager for a building construction project is planning to go on vacation
midway through the project execution phase. What should the project manager do first to
ensure the team is empowered and deadlines are met?
A project team was established for a community impacted by oil and gas exploration activities. The team is required to interact with several external stakeholders. The local council authority has requested a meeting with the project team to discuss the impact of the project on the community. The project manager was not available at the time of the meeting, and the team was in disagreement regarding who should attend the meeting.
What should the project manager have done to prevent this conflict?
A software system is being built for a company. Once the system is in production, the team would like to collect usage data to evaluate the delivered value.
Which evaluation practice should the project lead use to obtain accurate usage data?
A project manager receives a call from the customer's account manager requesting support for a critical operational issue. Although the issue is unrelated to the project, the customer believes that one of the project team members has the technical expertise to recommend a solution.
What should the project manager do first?
An important email from a project sponsor states that a backlog item should be immediately prioritized. What should the project manager
do with many tasks still open on the Kanban board?
A project manager has just taken over a project that is halfway through its schedule. In a brief meeting with the client’s key project team, the project manager receives several requests from a specific client team member who was not at the project team meeting. The requests for information seem to be for trivial information that was previously submitted in project documents.
What should the project manager do first?
A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?
A project manager works for a large manufacturing company with diversified domains. The project team often participates in change requests Recently, the change control board (CCB) deferred some requests and the project manager wants to communicate these requests to the stakeholders
What document should the project manager use to communicate these requests?
A project manager is working with an agile team. A key stakeholder who does not
join the sprint planning session is very unhappy, as the delivery date for the final product has
been pushed back three times. What should the project manager do?
In a fixed time and budget project the customer wants the development of a core component to be based on agile practices, as the final scope of (he requirement has not yet been fully developed. The project manager is participating in contract development with the sales team and wants to ensure that development costs do not impact the profitability of the project.
Which two controls should the project manager incorporate into the contract to specifically address the development of the core component? (Choose two)
In a functional organization, a product analyst is assigned to a short-duration application development effort The analyst expresses concerns about the task and asks the project manager to provide the support of a peer with expertise in this domain
What should the project manager do?
A project manager has been assigned to complete a worksite project that was started by a different project manager. The project is now in the execution stage. Upon careful review, the project manager realizes that the local community was not included in the stakeholder register, which has resulted in extreme opposition from the community.
How should the project manager handle this issue?
After a project learn has been working on a project for several months, the project Is cancelled The project sponsor Is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.
How should the project manager handle this situation?
A project team is conducting a retrospective. The team wants to identify what had
a positive impact on the velocity and keep doing it.
Click on the area that the team should focus on to identify good practices.
An agile project is starting its seventh out of eight iterations In a planning meeting, the team realizes that an unidentified risk became an issue and the contingency reserve has to be used.
What should the project manager do?
A team has been working together for several months and has successfully
delivered work. A new team member has joined the team but is having difficulty
contributing.
What should the project manager do to help the new team member integrate effectively?
A new team member on a self-organizing team is finding it difficult to deliver due to the new technology being used in the project. What should the project manager do in this situation?
Since the beginning of a project, the product owner keeps asking during ceremonies about the budget spent for each product iteration The product owner seems much more interested in the cost rather than the product itself.
What should the project manager have done earlier to change the product owner's behavior''
A business analyst on the project meets the customer in the elevator and says that due to constant changes in requirements the development of the product will take more time than expected What should the project manager do?
In a global project, the project manager has to plan and manage communication between the team members and stakeholders in order to ensure the project will remain on track and achieve its goals.
What should the project manager do?
At the closing phase of the project the project manager sends the completion reports to the client as a formal written document, indicating that the contract has been completed The client refuses to approve the document since the defect rate is 0.1%. The project manager insists that it is an acceptable rate as the standard defect rate of the industry is 0.15%.
What should have been done to avoid this situation?
A project manager prepared the base budget model to deliver a highly
customizable software solution. The solution will be delivered in multiple countries with
significantly different cultures and will be staged over phases.
What should the project manager do next?
The project manager has initiated the project and the team's roles and responsibilities have been assigned. In preparation for the development of the project management plan, the project manager reviews lessons learned from previous projects and discovers that the same team has been missing delivery dates.
What should the project manager do to ensure timely delivery?
In a multinational project, stakeholders are in different time zones. The project
manager has regular project update meetings with the stakeholders. However, a group of stakeholders who has never attended project update meetings is complaining to the
project sponsor that they know very little about the project.
What should the project manager do?
A project manager scheduled a session to identify risks on the current project. Most of the stakeholders did not attend the meeting, although they previously confirmed their attendance.
How should the project manager proceed in order to complete the risk register?
A project manager has been asked to participate in the procurement process for a
software application that allows customers to buy online e-learning courses. The project
manager will take over the project once the supplier has been sourced.
What should the project manager do before the project starts?
An agile project has just started, and the backlog is being prioritized. The
customer wants to prioritize business value over identified risks.
How should the customer’s request be managed?
A project started 12 months ago and is currently on iteration 12 of 14. The team
has performed well and completed all deliverables on time. However, some team members
are starting to complain about the length of the project, creating a risk for lack of
performance at this critical stage.
What should the project manager do as a servant leader to mitigate this risk?
A new project manager has been assigned to a project that is in danger of failing The stakeholders do not know the project status nor do they know what benefits will be delivered by the project.
How can the project manager convey these benefits to the stakeholders?
A project manager for an agile project wants to have a highly engaged team. How should the project manager achieve this objective?
A project manager has just been assigned to a project to build new software for a client. All the requirements have been gathered.
What should the project manager tell the team members to focus on?
A newly hired team member just joined the project team and reports directly to the
project manager. In the first week, this new member tells the project manager that there is a
task priority conflict with hard, dependent tasks on the critical path.
What should the project manager do to handle the conflict?
On a transformational project, the project manager is confronted with resistance
from the stakeholders. To overcome this and gain acceptance of the change, what should
the project manager do first?
A senior management team member contacts an agile project lead and mentions
that certain features the senior manager thought would be in the current release were not
included. What should the agile project lead do?
The project management office (PMO) assigns a project manager who specializes in hybrid approaches to a predictive project that is off track from both the cost and schedule perspectives. The project runs into further delays as the project manager is ramping up on the project. The stakeholders and ask senior management to replace the project manager.
How should the project manager approach this situation?
An agile project is running its fifth iteration out of 10. After the last retrospective, the team members realize that they had to work extra hours to deliver the committed work What should the project manager do?
A project manager has two projects that are being executed at the same time. The duration of the critical project must be reduced, but the project manager does not have enough resources to achieve this goal. In addition, the schedule does not have activities that can be overlapped.
What should the project manager do?
A project manager is assigned to a hybrid project involving multiple sectors. The sectors collaborated in the joint venture delivery facility.
The chief executive officer (CEQ) from each participating sector is a sponsor of the project. Each sector nominated project representatives, who in turn appointed a product owner who was the most experienced in delivering such projects.
Match the stakeholders on the left with the appropriate frequency for updates.
A project manager is assigned to a strategic communication project that involves
subject matter experts (SMEs), interns, and new recruits. The project manager discovers
that the project is not gaining much traction due to knowledge gaps from the interns. The
budget for training is exhausted and the project needs to be delivered without delay.
Which two actions should the project manager take? (Choose two)
A project team member complained to the project manager that they are not sure f on the latest requirements document because it was emailed to them about one week ago. They mentioned that, in the past they worked on a document tor more than 20 hours only to find out later that another team member had already updated that same document but did not send them the latest revisions.
What should the project manager do to avoid this situation in the future?
In a weak matrix environment, two key team members are falling behind with their tasks, which will affect the success of the project.
Further investigation by the project manager reveals that they have unresolved issues with each other. The project manager asks them to find a way to resolve the issues, but this is unsuccessful. The project manager then holds a meeting with them to work outa permanent solution to the issues, but this is also unsuccessful.
What should the project manager do next?
A project manager is working on a major construction project. Part of the
agreed-upon plan was to use a cloud-based system with a server that runs on high-speed
internet service since most of the team members work virtually. The company needs to
reduce operating costs as much as possible and management insists that the project will
now use a system running on a conventional dial-up service.
What should the project manager do next?
A company's leadership team has decided to invest in a new product using an agile approach The commercial and product teams have started the planning activity for this new venture Which three key factors does the project manager need in order to deliver this product? (Choose 3)
A project is being initiated, and almost every resource available on the project team is a recent university graduate. What should the project manager do to ensure their engagement with the project?
An agile project team discovers that they are unable to implement a feature completely in the first iteration The team believes it may not be able to complete the tasks in the second iteration. The feature is a critical component that the customer has prioritized.
What should the team do?
A project manager has just been assigned to a team that is developing a new design product. The work breakdown structure (VW/BS) has been created and the activities have been assigned to the team members. The project manager finds that there are activities that could be completed sooner by other team members. If the current assignments are left as is, the project could be delayed 2 weeks.
What should the project manager do in this situation?
A contractor has been making small changes to the engineering specifications without submitting change requests. The contractor and the technical team did not discuss the changes with the project manager, and the modifications do not affect the budget and quality of the deliverable.
What should the project manager do?
Early in a project, a team member failed to effectively communicate the reason for their absence from three team meetings. How should the project manager handle this situation?
A new project manager is assigned to a project in the execution stage. A few key stakeholders inform the new project manager that the project has some serious issues.
What should the newly assigned project manager do first to understand the issues?
During a meeting for product review, a key stakeholder announces that because they are receiving adequate information about the project they will not attend any further meetings. What should the project manager do?
A key stakeholder is upset because the final product delivery has been postponed for the third time. The project manager meets with the stakeholder and discovers that there is a risk of revenue impact if a new feature is not released in 1 month.
What should the project manager do?
A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is
seeking the project manager's recommendation on how to approach this request.
What should the project manager do to help the product owner?
An organization is undergoing an agile transformation. The executive leadership team is concerned that they will lose control over the scope of the project.
What should the project manager, who is responsible for this project, do to mitigate this risk?
A project stakeholder has left the company. The new stakeholder is a family member of one of the team members. This stakeholder does not attend meetings. The project manager finds out that the stakeholder has been asking the family member for project updates.
What should the project manager do?
A project manager is working on a project to build a manufacturing complex. The project will run in three different phases: engineering, procurement, and construction. The
procurement phase is in the initiation stage. The project sponsor wants to pursue the project phases as they have been planned, but also wants to accommodate and adjust to new data, input from the customer, and changes during the various phases as the project progresses.
How should the project manager approach this project?
A project manager identifies a risk that has a high probability of occurring. How should the project manager manage this risk?
During regular project progress review meetings, one team member shares bad news that has a significant impact on the project schedule. How should the project manager
react to ensure the project remains successful?
A project manager collects various pieces of information and consolidates metrics in an agile project. The project manager finds that there is slack in the team in terms of productivity. The number of items sent to development per person has decreased by 10%, and the project manager used a root cause analysis (RCA) and discovered the reason is a lack of knowledge in one of the frameworks used for modeling.
What should the project manager do next?
A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed
for the product.
What should the project manager do to continue with the delivery plan and return to the expected velocity?
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the
company’s competitive advantage. What should the project manager do?
A project manager is managing an agile project that is part of a program with many interconnected projects. Dependency management is fundamental because there will be many milestones for different projects that are dependent upon each other during the program duration.
What should the project manager do?
A project manager is managing a few innovation projects with a high level of uncertainty. The project manager is experiencing challenges with the large number of change
requests issued due to the nature of the project.
What should the project manager do?
A team needs to follow defined cybersecurity compliance that is mandatory for a customer project. What should the project manager do to monitor compliance in the
project?
A construction project for a nuclear power plant will reduce the region's energy dependence on external electricity supplies. The project manager has received support for
the project from several leaders in the region. However, some people from the government want to stop this project to focus on developing renewable energy sources.
Which stakeholders should the project manager include in the stakeholder engagement plan?
A company is running a project to eliminate a sales channel that has been unprofitable for the past 3 years. A key stakeholder from another area, who has legacy ties to that sales channel, objects to the project.
What should the project manager do in this situation?
During execution of an agile project, a project manager realizes the budget is almost completely used, but the project is not close to being completed. What should the project manager do to address this concern?
A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.
What immediate corrective action should the project manager take?
A project manager has been assigned as the servant leader for an ongoing project that historically has presented unexpected problems. The main stakeholder is hesitant to continue with the rest of the sprints even though there are no open issues or indications of risks at this stage.
What should the project manager do to address this problem?
A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.
Which risk management process should be performed?
A project manager is leading three projects in a program focused on starting product commercialization. Once the three projects fareket, the project manager stops attending the recurring team meetings. The program manager asks the project manager to continue attending these meetings to maintain those team touchpoints.
This request does not match the project manager's expectation, since a program manager is overseeing the remaining work
How should the project manager approach the situation?
A project manager has been assigned to a software development project that will undergo several iterations until the customer is satisfied. Match the tool or technique on the left that the project manager should utilize to ensure tasks are efficiently managed to the correct task on the right.
A company has undertaken a large transformation project in preparation for the changing economy. During the planning of the transformation project, the key resource from human resources (HR) refuses to approve the proposed project plan.
What should the project manager do to gain an understanding of the cause for the resource's refusal?
A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with
incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.
What should the project manager do first?
The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to ‘move its go-live date. What should the project manager do next?
A project team is struggling to obtain the required data for a complex project in order to proceed to the next stage. What should the project manager do?
A sales manager submitted a new feature request to the product owner, and the request was added to the product backlog. During the sprint planning meeting, the team struggles over which algorithm is the most efficient one to use. The team thinks that some development work is needed to decide.
What should the project manager do?
A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.
What should the project manager do?
A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the
beginning of the project have changed.
What should the project manager do?
A company changed the product owner on an existing project. The new product owner has less knowledge of the product than everybody else on the team. Due to the product owner's lack of knowledge, the team does not consider the opinions of the product owner seriously and mostly relies on the project manager's opinion.
What should the project manager do?
A project manager has begun a complex oil refinery project. Although the project is in the initiation phase, the sponsor keeps asking for concrete dates for the most important project milestones.
When will the project manager be able to provide the requested information?
A project manager is leading a project that has been in execution for 1 year. An experienced team member is performing well, but often disagrees with the project manager and refuses to implement their decisions. Part of the team supports the team member's defiance, while the other team members do not.
What should the project manager do?
A project manager is leading a multiyear project that involves internal and external stakeholders. As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.
Which three actions should the project manager take to ensure proper stakeholder involvement? (Choose three)
A project manager holds meetings every Monday to review the team members' progress. The project sponsor is insisting on daily updates to ensure improved delivery on products developed by all of the teams, including this one. Some learn members indicate they are on a very light time line and would attend me Monday meeting, but not the daily update meetings.
What should the project manager do to ensure all team members participate in daily meetings?
During project planning, a development team is assigned an agreed-upon work package to determine the appropriate pattern for integrating a new service with a legacy system. The lead developer has requested a meeting with the project manager and Is looking for direction as to which technology to select.
How should the project manager help guide the lead developer?
A healthcare organization hired a new compliance specialist to ensure that the healthcare compliance needs are met. The feedback about the new compliance specialist
from the team was average.
What should the project manager do to help the new compliance specialist improve?
A project is designed to provide local community members with health facilities that will support improved sanitation practices. What should the project manager do to
ensure the community members are up to date on project progress?
Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.
What should the project manager have done to prevent this situation?
A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.
What should the project manager do?
A project manager is assigned to an agile project that has an aggressive time line and a fixed budget. Currently, the majority of the items are in the backlog and only a few are in process or completed.
What should the project manager do?
An IT project manager for a project that is 50% complete teams that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?
At a recent steering committee meeting, the project sponsor asked the project team to add a major feature to the final product. After consulting
with the project team, it is determined that the change will cause significant impacts to the original project delivery date and budget.
What should the project manager do to assess the priorities and meet the new objective?
Halfway through project execution, stakeholders ask for equipment that was expected to be procured. The project manager explains that the equipment was purchased, but differs from what the stakeholders are currently asking for. This is because the initial requirements were changed during a previous meeting.
What should the project manager have done to avoid this situation?
A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The
project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?
An iteration is almost finished, but the team is struggling to complete the stories that require more time. What should the project manager do first?
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team
Which two actions should the project manager take? (Choose two)
A project manager receives an email from a customer saying that they do not want to keep working with one of the project team members. The customer does not provide
any reasons for this sentiment. The project manager is concerned because this project team member is highly skilled and experienced and is key in one of the main project deliverables.
What should the project manager do to ease the situation?
A technical team for a project is managed by the lead who was recently promoted to this role. Inside the team, a mature and experienced engineer is constantly questioning the actions of the team lead and is currently ignoring part of the team lead's decisions. The team lead asks the project manager for help.
What should the project manager do?
During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the
required IT system. What should the project manager do?
A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle
What should the project manager do next?
A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety
approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.
What is the appropriate flow for product development?
A project manager is facilitating a project steering committee meeting where the prioritization of work items in the backlog is being discussed. The
engineering executive wants to prioritize features based on level of effort, completing the smallest items first. The quality executive wants to
complete the most complex tasks first to have adequate time to ensure a quality product is delivered. The compliance officer wants to complete
items with associated regulatory components as they are essential items.
How should the project manager prioritize the work items?
An experienced project team member always points out the issues of other team members during meetings. The other team members feel that
the experienced team member is deflecting their own issues in meetings.
What should the project manager do?
An agile team is facing a challenge with the quality of its deliverables. Every time a feature is promoted to production, many defects arise, preventing the customers from properly using the solution.
What should the project manager do to avoid this situation in the future?
A project's business case was just approved and the project manager is creating the benefits management plan. It is unclear how the benefits from the project align with the organization's vision.
What should the project manager do first to verify alignment?
A proof of concept for a proposed solution was conducted during the project implementation, and it was determined that the current technology cannot support it. What should the project manager do next?
During the development phase, a team member encounters an issue with a specific task and attempts to resolve it for the next several days. The other team members ask
the project manager to reassign the task to another team member to avoid jeopardizing the target date. The current team member assigned communicates they will feel frustrated if the task is reassigned to another team member.
How should the project manager address this situation?
A company has decided to initiate a project to eliminate a sales channel that has been unprofitable for the past 3 years. Some members of the project team are pessimistic about the project.
What should the project manager do in this situation?
The project manager's firm is executing a construction project. The project is stalled due to reemerging conflicts and misunderstandings among stakeholders.
What should the project manager do to ensure a smooth start and completion of the project?
During the last iteration of a hybrid project, one of the key members of the team wants to leave the project. What should the project manager do to address this concern?
A team averages 100 story points per iteration. The team estimates there are about another 2,000 points remaining and about 20 iterations remaining. One of the team members suggests estimating by feature because the large stories are difficult to break up.
What should the project manager do?
A project manager Is leading an agile software development project with strict deadlines The client complained that the last deployment did not meet the acceptance criteria The development team lead is arguing that the deployment met all specifications and has provided evidence of the client's specifications
What should the project manager do?
A project manager is building a team that will be comprised of subject matter experts (SMEs) from two different divisions of the same company.
The project team will be virtual and will include members from different countries around the world.
What should the project manager do to ensure effective team building occurs?
project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?
A bank is considering building another branch in one of three neighboring cities. The project manager has been tasked with demonstrating the benefits of building a new branch, renting an existing building, or not expanding at all.
How should the project manager proceed?
A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.
What should the project manager do next?
A key stakeholder has recently started in a company and has been assigned to a hybrid project. Although very experienced in their domain, the stakeholder has only been exposed to predictive project approaches.
What should the project manager do?
A project manager is consolidating information tor all the workstreams within a data center and IT service transition project To ensure the project delivers value quickly the project manager will assess a large number of consolidated project schedules
Which two actions should the project manager take with regard to schedule analysis? (Choose two)
A supplier informs the project manager that producing the quantity of a key component for the project will require an additional month. The project manager has to meet an important
milestone in a week.
What should the project manager do next?
A project team is implementing a new solution that will be distributed worldwide. Due to a new issue that has a global impact, several government agencies are implementing new regulations that will affect the solution. The project manager must assess and prioritize the impact of these changes on the project scope/backlog.
Which analytical tool can be used by the project manager to define this scenario?
A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,
What should the project manager do?
A quality Issue that requires a change to the quality standard Is encountered In a project Currently, there Is no budget available for the required changes. What should the project manager do?
A project manager is working on a project that will transform the organization's operating model. The project manager reviewed the budget allocation for various phases and was informed that upper management will not approve any additional funds.
Knowing that there are no additional funds available, how should the project manager proceed?
A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.
What should the project manager do?
After months of careful planning and discussions with subject matter experts (SMEs). a new law is announced that may significantly impact the project budget. What should the project manager do first?
A new product is designed for a certain market. This product needs to adhere to the health and safety regulations for that region. What should the project manager do to ensure that the product complies with the regulations?
A protect is going through its iterative design stage One of the team members has been performing poorly. This is a critical project for the company and execution is about to start What should the project manager do?
A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team
What should the project manager do?
A project is almost completed, and both the sponsor and the project management office (PMO) are happy with the project manager's performance reviews. The project manager is under budget and ahead of schedule. However, a team member asks to add a feature to the product that will make the product more impressive and acceptable to the end users.
What should the project manager do first?
A third-party supplier demands payment for the services provided for a project. The agreement was that payment would be made after the organization receives payment from the client. The third-party supplier lacks the capital to meet their payroll and has informed the project manager that if they do not receive payment quickly, they will withdraw team members from the project.
What should the project manager do?
A project is experiencing delays due to identified risks What should the project manager do to manage the project schedule?
A scrum master is receiving conflicting status updates for the same task How should an accurate status be obtained from the team?
A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to
take action in advance to ensure the project succeeds.
What should the project manager do?
A project manager is about to start a large-scale project with unclear requirements, a fixed deadline, and a fixed budget. The client is unable to provide a product owner, as they do not have enough capacity and they want to be involved only a few times during the project.
How should the project manager plan and manage the project?
A company is transitioning its projects from a predictive to an iterative approach. The protect team is complaining because they are unsure of what needs to be done due to all of the changes requested by the product owner for features already developed since the beginning of the project.
How should the project manager handle this situation?
A customer is meeting with an agile team at regular intervals and keeps changing priorities for the team members. What should the project manager do to remove this impediment?
A project manager sent the first communication about the project management plan to the team. The next day. two field engineers were asking about their roles and the project schedule.
What should the project manager have done*?
A project manager works in a startup company and is in charge of a key project that has critical and time-sensitive delivery objectives. One of the project team members missed completing an assigned deliverable on time, despite repeated assurances from the team member that it would be completed on time
What should the project manager do next?
A project manager has been assigned to an emergency project that must be completed within the next few weeks. The project manager realizes this will have an impact on the local community. As the work is near a school, the project manager has engaged with them to understand their needs
How should the project manager ensure the work continues smoothly?
A project is nearing completion. The sponsor is already asking the project management office (PMO) when the project manager will be assigned to host a planning session for a new initiative.
What should the project manager do next?
A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit
Which two rules are appropriate tor the project manager to instill in the team? (Choose two)
A protect team member is having difficulty delivering assigned tasks for a project that is at risk of being delayed The main issue is that the team member does not understand a new system that was recently implemented
What should the project manager do?
An IT project manager has been referred to a new, highly rated vendor that provides quality assurance professional services, The project manager plans to engage the quality assurance vendor on a new project, but their rates do not fit into what was budgeted for the project.
What should the project manager do next?
A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully What should the project manager do next?
An agile team has completed 9 out of 10 stones tor the sprint. During the retrospective a few team members pointed out that they finished a of their stories However one team member tailed to finish a story
What should the agile leader do1?
A project requires the installation of a call center to support operations. It is estimated that the call center will need 100 people working on
weekdays from 8:00 a.m. to 5:00 p.m. and weekends from 8:00 a.m. to 12:00 p.m.
What should the project manager do?
As a result of updated external regulations a project manager has been asked to upgrade the operation system tor a call center The project manager is beginning to meet with and segment the stakeholders involved
How should the project manager categorize the call center staff? Click on the correct section of the power/interest grid.
A client comes to the company asking to copy a project that was executed 2 years ago
in the same city, with the expectation that the new project will have the same cost and duration.
While finalizing the project management plan, the project manager realizes that the baseline
costs are much higher than the original project.
What could the project manager have done to avoid this?
Two companies recently merged. The team charter for a new initiative combines the best practices of both companies. One of the team members consistently ignores one of the rules.
What should the project manager do to address this concern?
During a status review meeting a team member raises concerns about tasks that are not being completed due to an underperforming resource on the team. What should the project manager do first?
A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.
What should the project manager have done to avoid this?
A project manager became aware of misunderstandings between a key stakeholder
and a team member with regard to some of the features defined in the project scope. What
should the project manager do?
During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level
What should the project manager do next with this opportunity?
During the design phase, a project manager realizes that the project will benefit from using adaptive tools The effectiveness of this approach has been proven in past projects inside the organization
What should the project manager do first?
A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing
What should the project manager review?
The client will not agree to closure, claiming that the project team has not performed the code inspections mandated in the development contract. The project team has performed the code inspections, however the records are not complete What should the project manager do?
A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials
What should the project manager do next?
A project manager is starting a project using a hybrid approach and notices some team members only have knowledge of predictive approaches What does the project manager need to do first in order to have good project performance?
The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders
What should the project manager do first?
An agile team has been struggling to keep up with the planned pace, which is frequently resulting in sprint failures What should the project manager do to help avoid this situation in the future?
Some of the mote experienced members of a project team have complained about the project manager The senior project team members feel that the project manager is micromanaging them and preventing them from completing their work.
What should the project manager do when made aware of these issues?
After the second iteration of a component development project, the project team conducts a retrospective It shows that in the initial phase the project has failed to comply with a product functionality. The planning for this product has a predominantly predictive approach.
Which technique will help the project manager to accelerate the deliverable?
The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources
What strategy should the project manager use in order to keep delivering value in a restricted environment?
A company is implementing a new system The project manager has identified that it is best to complete this project using a mix of Scrum and Kanban methodologies The product owner is confused as to how to start delivering the functionalities required
How should the project manager assist the product owner?
A project manager receives a voicemail from a business analyst on the project team The business analyst indicates that an internal stakeholder is upset that they were not included before the project began The stakeholder is asking for an addition to the requirements traceability matrix
What should the project manager do to improve the stakeholder relationship?
A company just started managing a project using an agile approach Due to this change the general manager is worried about the scope definition process for upcoming projects
What should the project manager do to ensure the project scope is completely defined?
During the daily meetings with the team the project manager notices that a new team member is not making the expected progress on an assigned task What should the project manager do?
During an inspection, the production phase was stopped because the inspector claimed that regulatory labels were missing. What should the project manager do?
A technical subject matter expert (SME) identifies an occurrence that should be captured in the project's lessons learned The SME asks the project manager to write, document and include it in the lessons learned register
What should the project manager do?
A project manager has been assigned to an education project with the objective of training a workforce in application development One of the deliverables is to provide internships to the best students in the customer's active projects However the customer does not have enough projects in progress right now The project manager decides to create several internal projects in order to ensure the internships
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose three)
A project manager works with a global virtual team. The team is facing difficulty in communicating with each other and often misses important messages. This difficulty leads to missed deadlines.
What should the project manager do to enhance project team effectiveness?
A project for Company A was successfully delivered within scope schedule, and budget by the end of the last iteration However during the project celebration ceremony, one of the business stakeholders says they perceive the project as a failure as it did not add any business value.
What should the project manager have done to avoid this perception?
During the execution of a project, the finance team identified that they were not involved in building the business case for the project and will not approve the estimated return on investment (ROI). What should the project manager do?
A project manager is assigned to a new marketing campaign The sponsor gives the project manager an approved project management plan for review and explains the scope, business requirements, deliverables and stakeholders The project manager asks to see the project charter to gain a better understanding of the project. The sponsor says the project is small and simple so there is no need for a project charter.
What should the project manager do?
A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using
What should the project manager have done to avoid this issue?
A new team member is added to a self-organizing team. The new team member is reluctant to speak and take part in team discussions or decisions.
Which two actions should the team take to engage this new team member? (Choose two)
A company's project management office (PMO) is incorporating more adaptive technologies and has hired a new project manager with hybrid project management experience The team is slow in adopting the new methodology and has not been updating project artifacts in a timely manner.
Which action should the project manager take to improve the team's performance?
As a member of an organizational change management team, a project manager must pass on any changes to the project team The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change
What should the project manager do?
An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost even though it is within the project budget.
What should the project manager do to resolve this issue?
During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43
What should the project manager do?
A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel
How should the project manager handle this situation?
The programming activities of a project were planned to last 35 days per module but the programming of the first module has taken 45 days What should the project manager do?
A project is in the knowledge transfer phase, and a few subject matter experts (SMEs) went to the client site for knowledge transfer The SMEs captured various process deviations without sharing with the project team
How can the project manager ensure knowledge transfer across the team?
In the beginning of project execution, the project manager finds out that a key resource will be unavailable for two weeks which could cause a delay to the schedule What should the project manager do first?
A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information
What should the project manager do first to resolve this situation?
A company has a lot of experience with predictive projects The project management office (PMO) has been trying to implement iterative tools within the project management framework, and the project manager has been asked to use these tools in their current project After the successful implementation of the iterative tools, the PMO asks the project manager to determine the benefits these tools brought to the project.
What should the project manager do?
A transportation company is transforming its operational processes and the mam system this company uses to move freight The scope statement is in place An iterative delivery approach has been agreed by all stakeholders. What does the project manager need to do next to help the team understand the work that needs to be done?
A stakeholder on a project has a reputation for being easily angered and unreasonably difficult on projects The project manager would like to minimize the impact of the stakeholder’s behavior on the development team.
What training should the project manager choose for their team to help with this situation?
A retail chain is evaluating a project to replace payment systems across all its stores in multiple locations The project does not pass the financial threshold but is also expected to increase market share, improve customer services and retain more customers The project is planned as a phased implementation building on learning from the retrospectives during each phase
How should the business increase the value of the project?
A project manager has been asked to lead a project. The performing organization does not have a project management office (PMO) or formal governance policies procedures, and guidelines for this type of project
What should the project manager do first to determine a governance approach for the project?
During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice One of the client representatives, who is not a key decision maker, is extremely opinionated This client representative could become a roadblock to progress due to their perceived level of authority during meetings
How should the project manager handle this moving forward?
A project manager is managing a complex research project with a high level of uncertainty A request is made to implement a mechanism to measure the quality of the deliverables.
Using a hybrid approach, what techniques can be used to achieve this goal?
A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not clear that it will deliver the expected value After some analysis the project manager discovers there is a mismatch of competencies in one of the teams
What should the project manager do?
An experienced project manager is overseeing a merger and acquisition project. The project manager reacted differently to different threats identified on the project
Drag the mitigation strategy on the left to the project manager's actions on the right
An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply
Which two actions should the project manager take? (Choose two)
Five agile teams working together on a product recently performed release planning Midway through the project, each team showed that their progress was on track When all of the teams integrated at the product level, many integration issues were observed The overall product release progress declined with predictions showing the committed content will not be able to be accomplished
What should the project manager have done differently?
An agile project is running its fifth iteration out of eight After the last iteration planning the team was informed that there is a new competitor in the market and it is necessary to move faster to ensure market share is not missed What should the project manager do?
A project manager is assigned to a project in a company that is transitioning to agile Not all stakeholders believe in the project, and some stakeholders would like the entire project defined and planned out early in the project However the project sponsor needs a quick win to ensure the continuation of the project.
What approach should the project manager use?
The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk
What should the project manager do first to facilitate the approval of project requirements'?
During the implementation phase of a construction project, a key supplier went bankrupt and cannot supply the contracted material. This issue could affect the project schedule What should the project manager do first?
A key project stakeholder who was a big supporter and motivator for the project team is leaving the organization The project team is experiencing low morale and poor teamwork
What should the project manager do to improve morale?
The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>
What should the project manager do?
A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?
A multinational company has a plan to expand their business into a new country where they currently have no presence A project manager is assigned to initiate this project
After reviewing the business case, what should be considered first when developing an appropriate implementation strategy?
During the third iteration, the team encounters a major delay that has not had significant improvements over the last few weeks What should the project manager do?
While reviewing prototypes, the quality team found some deviations that do not affect the mam functionality but have the potential to be an issue in the future To avoid major problems in the future, the team recommends corrective actions that will require additional funds The project is already struggling to stay on budget and has even used some of the contingency reserves
What should the project manager do?
During the retrospective ceremony, the agile team is talking about the product owner’s expectations not being met What should the project manager have done at the beginning of the project?
A junior staff member was recently assigned to the team. The new team member tells the project manager that they are confused because they are not familiar with what is expected of them on the project
What should the project manager do to assist the new team member?
The tables show the requirements for an agile project with the anticipated return on investment (ROI) and identified project risks, along with the analysis details .
What should be the priority order in the product backlog?
A new project manager was assigned to a project during implementation. The project manager realized that new tax policies are creating a risk for a cost overrun by 25% The project manager updated the risk register and kept the project running as normal The CEO has announced that the project could be cancelled since the acceptable cost overrun is only 20%. The project manager was quite surprised as this was new information.
What should the project manager have done to avoid this?
A project manager realizes that a project is becoming delayed because some key decisions are affected by contradicting views between the organization's senior management and external stakeholders. What should the project manager do?
A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?
An organization is embarking on the deployment of a new digital solution that will revolutionize purchasing services The project manager has created all the necessary plans and activities to ensure a successful integration and solution launch There is a risk of a partner’s system being unavailable which could impact the project negatively
What key activity is needed to ensure the project's success?
A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch
On what should the project manager focus?
A company has assigned a project manager to the initial task of determining the resources required for a new project What should the project manager consult?
During the first project meeting with a new project manager, a stakeholder complains about not receiving periodic reports. What should the project manager do first?
An international client contacted a software development company to build out a
software product, and an agile project manager was assigned. At one of the review meetings,
the client complains that a feature mentioned at the initial debriefing was not implemented.
What should the project manager do?
A project manager is using a hybrid approach for a project. The project team created and reviewed the risk tog with the stakeholders at the beginning of the project However midway through the project, the project team and stakeholders became misaligned with the risks and mitigation strategies
When should the risks be reviewed to ensure alignment between the project team and the stakeholders'?
A project manager has experience working with a specific provider that has been
requested for an upcoming project. This provider often fails to meet deliverable dates; however, it is the only company with the specific experience required for the project.
What should the project manager do during the planning phase?
A project manager is leading an integration project for a retail company. The project
demands a lot of time from the stakeholders to make important business decisions. The
project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this
project?
A project manager entered into a contract with a vendor to build a new system. During the acceptance test stage, the project manager noticed that the system quality was not satisfactory-How should the project manager support their claim to the vendor?
A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.
How should the project manager address this?
The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two things should the project manager do? (Choose two)
A hybrid project is experiencing several issues with both the agile delivery of the
product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?
The sponsor approaches the project manager with new features they want added to
the project. The project is 95% complete, but the sponsor insists that continued support for the
project relies on the addition of the new features.
What should the project manager do?
One team member Is complaining about an agreement made during the last meeting. That team member was present at the meeting ana participated in the decisions registered in the meeting minutes.
What should the project manager do next?
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
A project manager is leading a project that is implementing an assembly line.
During the quality review meeting, a team member reports an issue stating that the product
being developed has discrepancies with the one requested by the customer.
What should the project manager do?
A project sponsor asks the project manager to explore a hybrid approach for a new
project. The product manager for this project has already prepared a detailed specification for the product.
What should the project manager do to proceed with the project management plan?
An agile leader notices that one team member consistently fails to complete the deliverables on time The agile leader suspects that this team member does not have the proper training.
What should the agile leader do?
A project manager recognizes that a key stakeholder is not engaged in the project and does not seem interested in the project status. The project manager is concerned that the project may go off track if the stakeholder expectations are not met
How should the project manager approach the stakeholder?
An organization is adopting an agile mindset. On the first agile project, the project
manager faced an issue because the team was unable to make decisions on time.
What should the project manager do to address the problem?
A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.
Which document should the project managefve?
An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives
What should the project manager do?
A project manager is leading a project in which key performance Indicators (KPls) are measured through earned value management (EVM). Match each measurement on the left with the correct category on the right.
A team is developing an experimental program to be used by the public. What should
the project manager do to ensure the desired benefits are achieved?
A project manager is working on a critical path activity and notices a delay in product delivery due to an anticipated event What should the project manager do first?
A project manager is defining the sprint goals with the team, A team member who is responsible for acceptance testing starts criticizing the goals and cannot come to an agreement with the other team members.
How should the project manager handle this situation?
A protect team has completed many iterations without proper sizing of the stories In some iterations the team sized some stories and completed them ahead of time In other iterations the team sized the stones but was unable to complete the planned activities
What should the team do differently during planning for the next iteration"?
A project manager is using a hybrid approach to comply with a regulatory requirement. The planning and closing phases will use a predictive approach, and the execution phase will use an iterative approach. During the second sprint review, the project sponsor requested a change in priority tor some of the product backlog items
What should the project manager do as a servant leader?
A project manager has been assigned with initiating a large project to deliver complex equipment Part of the project will be the result of a long research process, but once this is completed, the other part of the project must be incrementally delivered to the customer.
Which approach should the project manager choose for this project?
Two learn members are consistently having misunderstandings and find it difficult to work together. How should the project manager handle this situation?
A project manager is in the process of creating a strengths-based team and is
organizing a series of workshops to identify and document the strengths of each project team
member. During this session, there are multiple team members who are not actively
participating. These meetings are becoming futile due to a lack of participation.
What should the project manager do?
When a project manager is trying to determine a leadership style to use on a project what should they consider?
During a project kick-off meeting the project manager tells team members that they can attend a weekly progress meeting either from home or the office. Which intangible stakeholder engagement quality is the project manager embracing to manage relationships?
A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation
What should the project manager do next?
During project execution of a new IT solution, the testing of one feature was unsuccessful. The go-live milestone is now impacted due to this delay. Extensive analyses were performed, and there is no way to resolve the defects before the go-live date.
What should the project manager do next?
A project manager who is working with a virtual team needs to mentor an entry-level colleague. This team member informs the project manager that they feel demotivated and excluded from the team
What should the project manager do first to solve the situation?
A project manager is assigned to a new water treatment plant project that has been
delayed for many years. It is revealed in the project charter that the sponsors of this project
are from three different business units. This is the first time the sponsors have ever
implemented such a project.
What should the project manager do?
A project manager is leading an electrical project that spans five towns. The project
manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?
A project manager is leading an automation project. The project team is colocated
and includes people from both the technical and business units. The project manager
discovers that personal differences and work styles are affecting the project negatively.
How should the project manager address this?
A project manager is assigned to a project related to taxes, which will be managed
using an agile approach. By reviewing lessons learned from a previous project, the project
manager discovers that a key stakeholder is an expert on taxes and is willing to help.
How should the project manager leverage this information?
An agile team has started a new project. When should the project manager organize their first team retrospective?
A project manager is assigned to a new project and is allocated with virtual team
members. Later, two more members from a recently acquired company join as additional
resources to the project team.
In order to ensure that there are no potential misunderstandings, what should the project
manager do?
The start of a 12-month project has been delayed by 2 months The project has a fixed budget, deadline and product specifications. What should the project manager do next?
A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1 week.
What should the project manager do to benefit from the SME's presence?
A project manager has been assigned to a new project. There is one team member
who never says anything during meetings. After meetings, however, the team member sends
detailed emails with very good suggestions that help with project execution.
How should the project manager guide the team members?
An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.
Which two project events will assist the project manager to ascertain if this is the case? (Choose two)
During a product demo with key stakeholders, the team identifies that one of the functionalities failed to perform as expected What should the project manager have the project team do first to address the issue?
In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan
What should the project manager do?
A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.
What should the project manager ask the team to do?
A team is working on a hybrid project. Due to different interpretations of the project requirements, the deliverables are not aligned to the expectations. What steps should the project manager have taken to prevent this?
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concem9
A project team delivered a critical deliverable to the customer. The customer
complained that the maintenance manual was not included.
What should the project manager do next?
A member of the board of directors has asked the project manager for the estimated cost of the minimum viable product (MVP). The estimated cost is needed in order to get formal approval for this project
How should the project manager report this cost?
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
A team is given an agile project to build a conceptual product for a new customer.
While planning, the project manager is trying to determine the best way to show value to the
customer, as the technical requirements are not very detailed.
What should the project manager do to help the client understand the value delivered during
project execution?
Eight people have been working on a project for an extended period of time. The
scope has changed significantly and the product owner has been replaced multiple times. The
team members are feeling disassociated from the project.
What should the project manager do to ensure team alignment with the goals?
During the project quality control process, the project manager realizes that the quality management plan does not include how the final user will perceive the benefits of the new product compared with the actual product. What should the project manager do first?
A new project manager is managing a hybrid project. The project manager wants to be
a servant leader to support the team by removing impediments but is not receiving feedback
from the team about the issues and risks they are facing.
What should the project manager do?
A project manager is leading a project at a contracting company, and the project
team just completed an iteration. The product passed inspection, but an additional feature was added to the product. The customer notices the additional feature and thinks it will introduce new risks to the product.
What should the project manager do to avoid this situation in the future?
us graph describes the current performance of a protect in relation to cost and schedule. What should the project manager do to bring the project back on track?
A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward
What should the project manager do first at this pomp
Two team members are arguing about which technology they should use when implementing iteration tasks. The predictive approach was broken into several legations that need to be completed on time so as not to jeopardize the projects timely completion.
What should the project manager do to resolve this issue and help the team move on to the next iteration?
During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?
A project manager finds that there are knowledge gaps in the project team relating to the core competencies required to deliver the desired results. What should the project manager do to achieve the desired results?
A project to implement a new online landing platform has started After the first sprint, the project sponsor requested a change. What should the project manager do next?
The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.
What should the project leader do to solve this situation?
An information technology (IT) team is responsible for the validation and release of a product developed by the agile development team Due to other priorities for the IT team the releases are delayed
What action should the project manager take?
A project manager is working on a large project in another country and realizes that
only a few people from the project team are working on all of the releases. What should the
project manager do to prevent this in the future?
A team member has encountered a technical issue similar to the one faced in a successfully closed project However, the team member did not know about the previous project arte would like to resolve the issue on their own
What should the project manager do?
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?
A project manager Is working on the initial phases of a highly technical project that employs the "first of its kind" technology. Many of the key project stakeholders are unaware of the project objectives and their participation levels are poor. At every meeting, there are a lot of objections and queries raised that are taking the discussions to a different level, and a great deal of time is wasted
What should the project manager do?
A project leader is assigned to a new project and is asked to assemble an effective
five-member agile team. If the project leader has no restrictions, which team should they
choose?
A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables
What is the remedial action the project manager should take?
In an agile team, some of the team members are coming forward to ask for more
autonomy on the project. What should the project manager do in this situation?
A newly appointed product owner is working with a project team that is using agile
for the first time. The product owner is constantly disrupting various team members throughout
the day to discuss progress. This has resulted in the team feeling micromanaged and
frustrated because of the constant disruptions.
How should the project manager proceed?
During the sprint planning of a project, the team members have a disagreement
about the comparative size of the backlog items and if they would fit into the next sprint.
Considering a hybrid approach, what should the project manager do?
A developer who has almost completed a required product feature for a prototype
leaves the company in the middle of an iteration. What should the project manager do?
A key import supply has suffered a delay of 6 months. The delay affects a functionality that is needed to complete the project on time. The project manager learns from the project te«... that another team is working on a product that could work as a solution, but it is still a prototype
What should the project manager do to accelerate this solution?
During the project planning phase, a project manager called a meeting to discuss the
product backlog with multiple stakeholders who represent the end users in various capacities.
Only one executive manager attended the meeting.
What should the project manager do?
A project manager is developing a project baseline schedule and has started to
assign team members to the project activities according to their function. What should the
project manager do in this phase?
A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some
reserves needed
What should the project manager do to successfully complete the next phase?