In the middle of a construction project, the primary construction materials provider canceled the contract and moved to a competitor offering a higher price. The risk manager considers
this a low-impact issue because many construction materials providers can fulfill the project demands. However, after informing the stakeholders of this issue, the major investor is about
to drop their intention to continue executing the project. The risk manager does not understand their decision.
What should the risk manager do next to understand the major stakeholder's decision regarding the project?
The risk manager notices that in their workshops, most of the risks identified are threats. What should the risk manager do to increase the number of opportunities identified?
A risk manager notices that a risk owner is facing challenges implementing their response strategy and the costs are significantly exceeding expectations. What is the first thing the risk manager should do?
A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project's key stakeholders.
What is the first resource the project manager should reference?
Project stakeholders can often be risk averse with little to no knowledge of the risk process. How should a risk manager increase stakeholder risk appetite?
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model.
What is an effect of adding the correlation to the model?
A risk manager faces resistance as they try to implement the project's risk strategy. Some members of the project team believe it is a waste of time and money, What should the risk manager do?
A project has a S0S4 chance of a US$100 000 profit and a 40% chance of a US$100,000 loss. What is the expected monetary value for this project?
A risk manager was recently hired to assist with a mid-sized infrastructure project. The risk manager becomes aware that they have an inexperienced project team.
What two items should the risk manager have their team review in order to prepare for an upcoming risk identification workshop? (Choose two.)
In a large industrial business, an on-going system development project faces a previously identified risk. The risk is adequately managed by the risk manager, however there is still residual risk.
What should the risk manager do?
Some project risks are applicable for the project's lifecycle while others risks are only applicable to specific project activities. When should project risks be closed?
During a brainstorming session, a stakeholder identifies a risk that, if realized, could greatly impact their team. The stakeholder insists that this particular risk should be
mitigated to the greatest extent possible, however, the majority of other stakeholders feel that different risks have higher probabilities of occurring.
Which action should the risk manager take to address this risk?
A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but notices that the project charter, work breakdown structure (WBS). and scope statement are not available.
What should the risk manager consider?
The risk manager is facilitating risk planning activities with the team. The team is documenting all the check points along the way that might indicate delays on critical deliverables.
What is this an example of?
During a risk identification session, the risk manager notices that subject matter experts (SMEs) are reluctant to participate because some risks could expose the poor maturity of processes in other business units. Which risk analysis technique should the risk manager use?
A risk manager and relevant stakeholders have completed a risk response plan for a project. They have identified and planned responses to the known risks; however, a risk owner has identified and reported some residual risks not previously addressed.
What should the risk manager do first?
The project team is updating the risk register with the minimum acceptable level of exposure and impact for each risk. The team also wants to determine if they have reached the maximum level of exposure before they escalate the risk.
What should the team perform in this scenario?
The project team recorded a risk in the risk register indicating that weather-related delays may impact equipment delivery during project execution. When it is time to request the equipment shipment there is bad weather, but the client wants the equipment delivered anyway.
What should the project manager do?
A risk management professional is currently facilitating the risk planning process with the project team. To increase the breadth of considered risks, the team wants to include high-level and strategic project risks.
What should the risk management professional do next?
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in the response plan to help mitigate the risks?
A project manager has requested a risk manager facilitate risk identification on a project. While facilitating this effort, the project manager wants to ensure that stakeholders interact and provide their expertise so that an exhaustive list of risks is created.
Which risk identification technique should the risk manager use?
The risk manager conducted an updated Monte Carlo simul-ation for the project at the end of a phase. The simul-ation reveals a key activity is now on the critical path.
What recommendation should the risk manager make to the project manager?
A new risk manager has been assigned to a project experiencing delays, quality issues, low performance, and client complaints. The work is being completed with the
client's vendor, which apparently has been causing all of the issues.
What should the risk manager do first?
A new risk manager has been hired on a project and meets with the project director. The project director supplies the project's risk register and asks the risk manager for an analysis of its effectiveness.
What two actions should the risk manager do next? (Choose two.)
A complex project that had hundreds of risks is almost done. The project manager is closing the risks as part of the closing process. One team member mentions that there are important documents to be updated.
Which document will need to be updated?
A project manager has just been assigned to a new project. The project manager has been tasked by the project sponsor to ensure the project risks are closely managed. The project manager starts with developing the risk management plan.
What is the expected outcome of developing the risk management plan?
A project manager was informed that the testing of the latest component in the project's software update release was not successful. As a result, 1he delivery timelines for the software release wifi be delayed, The project manager did not previously capture this as a risk to the project.
What should the project manager do next to avoid similar risks?
The project manager has completed four projects all with similar scope. The project manager has recently been assigned to start on a new project and believes some risks may occur again on this project.
What should the project manager do?
A mega facility development project is evaluating some options to achieve the project schedule and budget. Each option's success is driven by multiple quantifiable factors.
What should the project manager do to evaluate and select the best option based on costs and probabilities?
Towards the end of definitive design, project costs have increased to the point where it will be classified as a capital asset project. The customer has expressed they want one final total project completion date and will afford no extensions after it is established.
How should the risk manager proceed?
During the monthly executive review meeting, the project sponsor would like to understand how the project team has planned to manage risks that were identified in the last meeting. What should the project manager do?
In a project to promote public health and mitigate health risks, the national health authorities intend to take actions to limit the risks of harmful insects by using pesticides; however, it is expected that some residents will have negative health effects due to the use of the pesticides but according to the assessment completed by the health authorities, not moving forward with this plan will have much more serious consequences on public health rather than following through with the original plan.
How should the project manager address this concern with the health authorities?
During a risk identification process in a construction project, the lack of space to install air conditioners is raised as a risk with high impact. Which is an example of an early risk trigger?
A project team identifies that there is a probability of missing a key milestone in a project. The team wants to move forward with the risk response planning.
What should the risk manager complete first?
A two-year project with a budget of US$2 million has completed about 60% of the work at the end of the first year. The actual cost incurred to complete the remaining 40% of work is about USS1.5 million. As a part of performing a specialized risk analysis, the calculated schedule performance index (SPI) is 1.2 and cost performance index (CPI) is 0.53.
How should the risk manager interpret such a low CPI value?
A risk manager is managing risks of a mission critical application. A subject matter expert (SME) asks the risk manager to treat every single risk identified as an extremely high priority.
What should the risk manager do?
Which statement describes the risk portrayed on the risk matrix heat map below?
A new risk manager is assigned to an ongoing project, what should the new risk manager do first to assess the project environment?