A tenant is moving into a new space in an existing building. They will fit out this new space and are considering LEED Certification. The tenant is projecting that 80% of the space will be used as office space. They will also have 10% of the space serving as a data center supporting the office. The remaining 10% will be used as a store showcasing and selling their consumer products for direct purchase to the general public. According to the Rating System Selection
Guidance, which rating system would be most applicable for this project?
A project owner has hired a Commissioning Authority (CxA) to develop a Commissioning (Cx) Plan which will be
submitted in the LEED application to document Energy and Atmosphere Credit, Existing Building Commissioning -
Analysis, Option 1. Existing Building Commissioning. At a minimum, what should be included in the Cx Plan?
A benefit of recommending LED lamps in an environmentally preferable purchasing policy is that they
What is the maximum allowed performance period defined for re-certification of a LEED Operations and Maintenance building?
The development of a five-year plan under Sustainable Sites Credit, Site Improvement Plan contributes to the achievement of
What strategy should be performed if submetering of the irrigation system is not available or difficult to implement for an existing building to comply with the Sustainable Sites Credit, Site Management?
Which of the following alternative transportation strategies help reduce pollution and land development effects from automobile use?
The project team is attempting to achieve Option 1. Lighting Controls in Indoor EnvironmentalQuality Credit, Interior Lighting. Which of the following is required documentation?
The decision to replace Chlorofluorocarbon (CFC) and Hydrochlorofluorocarbon (HCFC) refrigerants with alternative refrigerants
Which of the following strategies are eligible for reducing the landscape water demand in Water Efficiency Credit, Outdoor Water Use Reduction?
The compliant value of green cleaning products and materials is calculated using what factor?
Which of the following strategies is most important for achieving economic and environmental performance in a LEED project?
A building manager has purchased and installed new T8 (fluorescent) lamps throughout the project facility. All other lamps remained the same. The project building's average picogram per lumen hour decreased. A valid explanation for this change is that
What is the minimum percentage reduction from the baseline required to earn the exemplary performance point for the Indoor Water Use Reduction Credit, Option 2?
What credit rewards customers who change their normal consumption patterns in response to the varying price of
energy over time?
Which system can significantly reduce or completely eliminate the amount of potable water used for irrigation?
Rainwater harvesting can be used for which of the following credits or prerequisites?
Which of the following LEED AP Operations and Maintenance Water Efficiency Credits has exemplary performance?
Discussing the project goals to help identify the credits and options that the team should attempt is an example of
The environmentally preferable purchasing policy (EPP) required in the Materials and Resources Prerequisite, Ongoing Purchasing and Waste Policy should address the criteria in which Materials and Resource Credit?
When developing a transportation survey, a LEED AP must make certain that the survey instrument collects information
What information is required when adding a new space within a facility to the ENERGY STAR® Portfolio Manager?
For Energy and Atmosphere Credit, Advanced Energy Metering, which individual end uses are required to be metered?
When tracking waste data during the performance period for Materials and Resources Credit, Solid Waste Management - Ongoing, which strategy may be used to document total and diverted waste?
An organization pursuing LEED O+M certification for their headquarters has a renovation policy that includes strict requirements around the selection of building products and requires contractors working in the building to develop a plan for the diversion of waste produced during renovation projects. What must the organization add to their renovation policy to meet the requirements of Materials and Resources Prerequisite, Facility Maintenance and
Renovation Policy?
A manufacturing plant is increasing units produced and the number of employees annually. The building is documenting compliance with Energy and Atmosphere Prerequisite, Minimum Energy Performance, Case 2, Option 1. Path 2 Benchmark Against Typical Buildings Using Comparables. Which of the following should be used to normalize the building's energy use?
Indoor Environmental Quality Credit, Enhanced Indoor Air Quality Strategies requires a project building to employ permanent entryway systems. How long must the entryway system be in the primary direction of travel?
Instituting a policy to prevent erosion and sedimentation and restore any eroding soils is a requirement of which credit or prerequisite?
If a manufacturer does not specify the calibration interval for the utility meters used for benchmarking building energy performance, the assessment team may specify a reasonable calibration interval not to exceed
What calculation is used to achieve Materials and Resources Credit, Purchasing - Ongoing?
What must the project team do regardless of building type for Energy and Atmosphere Prerequisite, Minimum Energy Performance?
The project team has been directed by the building owner to only pursue practices that directly improve the actual building performance. Which of the following would be the lowest cost option?
Which of the following plumbing fixtures apply to the calculations in Water Efficiency Prerequisite Indoor Water Use Reduction?
Which of the following standards is applicable in order to comply with Indoor Environmental Quality Credit, Thermal Comfort?
Which of the following is an allowable method to increase cooling tower cycles of concentration?
Which of the following prerequisites or credits has a minimum occupancy requirement?
What percentage of individual occupant spaces must have individual lighting controls in projects seeking Option 1.
Lighting Control in Indoor Environmental Quality Credit, Interior Lighting?
What is the diversion percentage of ongoing consumables in order to achieve exemplary performance as specified in Materials and Resources Credit, Solid Waste Management - Ongoing?
Which of the following statements must be true in order to achieve the Water Metering Credit?
What is the maximum number of points a project could achieve using innovation credits for the Innovation Credit, Innovation?
A project is pursuing Materials and Resources Credit, Solid Waste Management - Facility Maintenance and Renovation. The project has generated the following waste as part of their Facility Maintenance and Renovation activities: 2,000 lbs. (907.2 kg) of steel, 900 lbs. (408.2 kg) of carpet, 1,100 lbs. (498.9 kg) of wood, and 1,500 lbs.
(680.4 kg) of wallboard. If the project has diverted 1,800 lbs. (816.4 kg) of steel, 900 lbs. (408.2 kg) of carpet, 1,000 lbs. (453.6 kg) of wood, and 250 lbs. (113.3 kg) of wallboard, what is the actual diversion rate achieved?
The measures called out on the following site plan may contribute to the achievement of which LEED credits?
(Click on Exhibit)
Exhibit
To determine possible credit compliance for Energy and Atmosphere Credit, Advanced Energy Metering, what information needs to be verified?