What is a significant difference between a halocarbon gas-based fire suppression system and an inert gas-based fire suppression system?
A new network storage device in a non-standard size rack of approximately 600 kg/1,300 lbs is going to be installed in the data center.
Are new floor loading calculations required?
When designing a data center network, your company wants to minimize the number of network switches to manage.
What type of physical cabling layout would be the best choice?
From the options indicated, what is the correct starting point for the raised floor installation?
A data center requires an audit to find out whether it conforms with ANSI/TIA-942 Rated-3 (concurrently maintainable).
Will the network architecture be part of this audit?
You are changing the design of the fire suppression system for your computer room from a halocarbon fire suppression system into an inert-based fire suppression system. Could you use the same formula to calculate the gas content for the gas?
A data center is located in an area where the demand for power is higher than the utility power company is able to deliver. This results in frequent power outages and, therefore, power shedding (scheduled/controlled power shutdown for areas) is frequently applied. The mains power is more than 650 hours/year not available.
What type of generators should be installed?
The location of a data center is just above the Arctic Circle (North Pole). The outside air temperature is never above 21°C/70°F.
Taking energy efficiency as the highest priority, which cooling system should you recommend?
The noise levels in the data center are approximately 91 dB (A).
Do employers need to take precautions?
The air intake of the mission-critical server at the top of the rack is measuring 25 °C/77 °F.
Is this acceptable?
The 'maximum exposed area' of the fire-rated glass is defined by the supplier as 3 sqm/32 sqft. The window area is 4 sqm/43 sqft.
What would be the best option?
You are allowed to use a calculator for this question. A battery bank is rated at a total capacity of 600 Ah. Calculate how much charging current the rectifier should be able to supply as charging current.
The logical overview of the data center looks as pictured. To what TIA-942 Rating is this design made based on electrical only?
The data center has been in operation for about 1 year and 2 months. The dust levels in the computer room are relatively high.
What is the most likely root cause?
What is the calculation for the desired attenuation factor for shielding material?