Black Friday Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65percent

Welcome To DumpsPedia

ASD01 Sample Questions Answers

Questions 4

Which of the following accurately describes best practice when work is sourced from an application’s workflow system?

Options:

A.

There is no need to use a Blue Prism queue as workflow is managed within the application

B.

Even though there is a workflow system managing and allocating work, a Blue Prism Work Queue should still be used

C.

Blue Prism cannot source work from an application’s workflow system

D.

When sourcing work from an applications workflow system, case data should be stored in an excel document

Buy Now
Questions 5

AnInsurance company has created 4 Blue Prism processes:

1. Change of Address

2. Claims Processing

3. Renewals

4. Order Letter

The Order Letter process is not a published process but is called as a sub process by each of the 3 other processes.

Each day at6am a scheduler starts:

  • 3 instances of the Renewals process on the same virtual machine
  • 2 instances of the Claims Processing process on 2 different virtual machines
  • 1 instance of the Change of Address process on its own virtual machine

How many licenses will be consumed by the running processes?

Options:

A.

7

B.

6

C.

4

D.

3

Buy Now
Questions 6

Which of the following statement combinations about Blue Prism memory management is correct?

Options:

A.

A Blue Prism Process reads a Business Object into memory as required. Once the called Action is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.A Blue PrismProcess reads a Sub Process into memory as required. Once the called Sub Process is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

B.

A Blue Prism Process holds a Business Object in memory for the duration of its run.ABlue Prism Process reads a Sub Process into memory as required. Once the called Sub Process is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

C.

A Blue Prism Process holds a Business Object into memory as required.Once the called Action is complete, the Process releases the memory for the .Net Garbage Collector to reclaim.

D.

A Blue Prism Process holds a Sub Process in memory for the duration of its run.A Blue Prism Process holds a Business Object in memory for the duration of its run.

Buy Now
Questions 7

VivaBank have an account closure process that can take up tothree days to close an account. All requests within the bank’s core system to close an account take place overnight during batch processing. There are two scenarios:

The timings relate to the expected automation time.

All requests will arrive in a BluePrism work queue from multiple channels using either web services or other Blue Prism processes.

The following detail from the Functional Requirement Questionnaire must be considered:

  • Cases must be processed on the same day if they come in between 08:00 and 22:00 Monday to Friday
  • Exception cases are to be emailed to the manual team during processing as and when they occur.
  • It is expected that up to 200 cases can be expected per day.

The Blue Prism solution consists of four processes and four Blue PrismWork Queues.

Cases come into the Account Closures Work Queue and are processed by the Account Closure process which determines if they are “Nil Balance” or “Balance to Transfer” scenarios. Before adding the case to the relevant work queue, a check ismade to see if an identical key has been added to the work queue today. If so the case is not added.

The Transfer Balance process work its queue and, for each successfully processed case, adds case to the Close Account queue.

The Close Accountprocess works its queue and, for each successfully processed case, adds a case to the Confirm Closure queue with the case deferred to 08:00 the next day.

The Confirm Closure process completes the sequence by confirming that the account is finally closed.

Ascheduler has been created to start all four processes at 08:00. Each process shall be configured to finish accordingly:

Please select from the statements below the ones you consider to be correct. (Choose two.)

Options:

A.

All processes should be merged intoone process to optimize licenses.

B.

Exception cases should not be distributed whilst the processes are running and instead should be distributed when each process has completed.

C.

There should be a separate work queue for each channel feeding the process.

D.

The Confirm Closure process should work until 22:00.

E.

As an alternative the solution could use just one queue instead of four.

Buy Now
Questions 8

Imagine a DR scenario where themain Production database goes down one afternoon. All processes use work queues and all new work is loaded first thing each morning. The database is backed up regularly but not in real time, so the restored back up will be slightly out of date, say by 1 hour.

If the backup was restored, and processes were restarted what would be the effect? (Choose two.)

Options:

A.

The processes would resume with the queue item being worked at the time of the incident.

B.

The processes would resume with the next available queue item.

C.

The queue item being worked at the time of the incident would be automatically marked as an exception.

D.

The queue item being worked at the time of the incident would need to be manually marked as an exception.

E.

The work queue would automatically ensure no cases is duplicated.

Buy Now
Exam Code: ASD01
Exam Name: Designing Blue Prism Process Solutions
Last Update: Nov 21, 2024
Questions: 27
$57.75  $164.99
$43.75  $124.99
$36.75  $104.99
buy now ASD01