A company's data center is being relocated to a different building. Who should be hired to ensure that the new location is properly prepared when the equipment arrives?
What is the most important factor to consider when upgrading the Building Management System (BMS)?
There has been a recent increase in complaints of items stolen from people's desks within a facility. What is the facility manager's initial step regarding the security of the staff and facility?
Which technology would be BEST to notify facility occupants during an emergency?
What is the purpose of a punch-list (defects list) walk-through in construction?
What is typically NOT included in the evaluation process for investments in new equipment?
What, in addition to vision, incentives, action plan, and resources, is required for the change management process to be effective?
What advantages can you gain by capturing and applying lessons learned in a multi-phased project?
Recently, an organization has flattened its structure versus that of a typical pyramid structure. As part of the restructure, the existing office building will be renovated. What type of design elements should a facility manager consider in the renovation?
What is considered the point in an asset’s life cycle where the total ownership costs are at the lowest?
During contractor evaluation, you discover their incident rate is below the industry average. What does this indicate?
The finance director has asked the facility manager to prepare a financial analysis comparing two alternatives for roofing system replacements. Each option has a different first cost, annual maintenance, and expected useful life. Which capital investment analysis technique would best consider the time value of money in the comparison?
A new hire has been provided with new uniforms and a $150 stipend to purchase new work boots. Within the first month of employment, the employee informs the manager that another job has been accepted and provides a two-week notice. What actions should the manager take regarding the material issuances?
A company's CFO has instituted a new accounting system, whereby part of the facility management funding is distributed to each department. The facility manager will assess each department for rent, utilities, and services. What is the billing of these expenses called?
You work for an organization that puts a strong emphasis on corporate values and being the employer of choice; truly valuing their people. The organization has put a lot of time and effort into ensuring that policies and procedures are in place to create an environment where employees are valued. This includes the company's performance appraisal system. How do you ensure the employees meet the expectations of the organization as well as your expectations?
Which is the MOST important best practice to ensure a successful safety culture?
Which standard would a facility manager use when assigning the floor area for occupant groups?
You have taken a position in a new country and do not speak the native language. However, your first task will be a facility renovation project. You need to become familiar with the standards, regulations, and laws that are applicable to a facility renovation project. What information source would be most accurate?
A facility manager may be responsible for status reviews on projects. Why are status reviews important and valuable?
What budgeting method requires a facility manager to use historical budget data?
What is the BEST course of action for a facility manager to take when an engineer continues to lag behind other engineers in productivity?
When developing a business continuity plan, the organization's leadership should establish a level of acceptable operations. What should be included in a plan to measure the expected level of success against the level of acceptable operations?
A residential complex next to a facility manager's building has complained about light trespassing from the campus area. What is the BEST action to take to minimize the amount of light that escapes from your property?
What approach should be taken to accommodate sustainability and customer concerns about installing flow restrictors?
What is an effective way to engage your staff in generating ideas that support the organization’s goal?
An organization is considering relocating from leased building #1 into leased building #2. Leased building #1 is 55,000 sq. ft. costing $1,100,000 annually. Leased building #2 is 50,000 sq. ft. costing $1,100,000 annually. Building #1 can house 500 people and building #2 can house 580 people. The company's benchmark is $2,000.00 per person per year for leased space. What is the MOST important reason to know what the company's benchmarks are?
The facility manager has been asked to provide a listing of all properties owned and leased by the organization. In which system does the information typically reside?
What is the first step in aligning the facility manager's strategy to the organization's strategy after assembling various inputs and producing the mission and vision statements?
What is the fourth stage in a well-established model of team development that consists of forming, storming, and norming?
Your company is evaluating a commercial office building for a new acquisition. What documents are the most important to review during the due diligence process?
A facility manager has developed a new health and safety program. What should be the next step?
Many large corporations prefer to locate a site and build a plant to meet their exact specifications. Because they prefer to invest their capital in their own business operations rather than real estate, they seek an investor who will buy the property and build. The company then executes a long-term lease with the investor. What is the resulting agreement called?
A landlord has just completed a major capital improvement in a multi-tenant commercial building. The property manager is responsible for determining if the costs of the project can be recovered from the tenants. What is NOT part of the process?
When during a major design project is the best time to provide your changes to the design team?
A company has decided to establish a long-range strategic facility technology plan. What is the first step in determining the future technology needs of the company?
What should be considered when developing a strategic facility management plan?
What may be impacted if requirements aren't captured correctly at the beginning of an Integrated Workplace Management System (IWMS) implementation?
What is the purpose of a punch-list (defects list) walk-through in construction?
As the Facility Manager, you secured 5,500 square feet of Class A office space on a multi-tenant floor to support a two-year business initiative. To minimize capital investment, the space will be used with pre-existing furnishings, fixtures, and equipment. However, before you can move people into this space, you will need a certificate of occupancy. What system must be examined to obtain a certificate of occupancy?
What functionality enables a Building Automation System (BAS) to support energy management during peak demand periods?
You manage a design-build project to renovate a new office space, including infrastructure upgrades. At the 60% design phase, the design-build contractor’s project estimate is over budget and contingency. What should be done first to address the issue?
What measures could you have taken to ensure your staff member focused on measurable priorities that you had established?
Part of your goals is to develop a succession plan for key positions within your operation, including yourself. What is most helpful in reaching this goal?
You are looking for ways to bring a project plan in on budget and on time. The project is still in the planning phase. At this time, the project's staffing is set up to be contracted for everything except project management. You think that human resources might be a constraint that you could change to re-balance the project’s budget. Where would you look for human resources that would help bring down the project budget?
Your senior leadership decided to implement an energy dashboard to track utility consumption. They want a baseline before commissioning has started to evaluate the results. How should this commissioning information be used on the dashboard?