Halloween Sale - Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 65percent

Welcome To DumpsPedia

CCP Sample Questions Answers

Questions 4

A work breakdown structure (WBS) is developed because:

Options:

A.

It avoids omissions of key product activities through a systematic planning process; removes the complexity of the project by dividing it into manageable units; and provides a framework.

B.

It defines specific tasks within a project from which schedules can be developed; it aids in linking activities with resources; it facilitates communication; and it allows integration of project plans

C.

It can be illustrated by individual bars for major phases, such as permitting, funding, engineering, procurement construction, commission/startup

D.

It can be illustrated by a simple bar, with important milestones represented by symbols at the planned time of occurrence

Buy Now
Questions 5

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the relative frequency of unit costs from Atlanta, GA?

Options:

A.

$40.59

B.

3

C.

$48.33

D.

33.33%

Buy Now
Questions 6

Some of the principles of good communication are:

Options:

A.

Seek to clarify your ideas before communicating; examine the true purpose of each communication; consider the total physical and human setting whenever you communicate; be mindful, while you communicate, of the overtones as well as the basic content of the message

B.

Tell the other person what to do; give insincere praise; psychoanalyze the other person; make light of a serious problem; do not gain the trust of anyone; always have a hidden agenda

C.

Use short words; avoid jargon; avoid acronyms and abbreviations; use complete sentences; have a beginning, middle and end; be accurate; be interested in what topic is being communicated

D.

The social process by which people in a specific situation construct meaning using symbolic behavior

Buy Now
Questions 7

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If $50 was invested at 6.0% on January 1, year 1, what would be the value of year-end withdrawals made in equal amounts each year for 10 years and leaving nothing in the fund after the tenth withdrawal?

Options:

A.

$6.80

B.

$3.10

C.

$5.35

D.

$2.22

Buy Now
Questions 8

The goal of listening is to:

Options:

A.

Analyze what the speaker is saying

B.

Find out what is going on

C.

Have time to formulate your thoughts on the subject

D.

Improve communication

Buy Now
Questions 9

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the method to estimate the cost of the new rides:

Options:

A.

Break down the technology into components

B.

Call vendors for quotes

C.

Use historical data from past projects

D.

Adjust known data from existing rides

Buy Now
Questions 10

The following question requires your selection of CCC/CCE Scenario 28 (3.7.50.1.7) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If the owner in A has a primary goal of completion within budget, the following contract types with the engineer/contractor would be best:

Options:

A.

Engineer — cost plus, contractor fixed price

B.

Engineer — cost plus, contractor cost plus

C.

Engineer fixed price, contactor cost plus

D.

Engineer — fixed price, contractor fixed price

Buy Now
Questions 11

The measure of number of units completed divided by work-hours consumed is referred to as:

Options:

A.

lined value

B.

Credit work-hours

C.

Productivity

D.

Cost performance Index (CPI)

Buy Now
Questions 12

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26 (2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Why is a +/- notation necessary when developing an estimate?

Options:

A.

Contingency cushion

B.

It makes up for the lack of time to develop a real estimate

C.

It is a government requirement

D.

There are unknowns that affect the final cost of a project

Buy Now
Questions 13

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Assuming a 53% tax rate, how much cumulative depreciation will have been claimed at the end of the grain elevator's life span?

Options:

A.

None

B.

$42,400

C.

$37,600

D.

$80,000

Buy Now
Questions 14

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of Year 3, steel prices will have increased by what percentage over today's price? (round to 1 decimal)

Options:

A.

8.7%

B.

8.2%

C.

4.6%

D.

8.0%

Buy Now
Questions 15

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

10,278 hours have been expended to date. The CPI at this point in time is 0.93. SPI is 1.03. How many hours were planned?

Options:

A.

10,586

B.

9,280

C.

9,559

D.

10,278

Buy Now
Questions 16

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

The entire pipe has been received, hangers have been installed, and all pipes are in place. None has been welded or flushed. What percent complete is this project?

Options:

A.

45%

B.

50%

C.

95%

D.

30%

Buy Now
Questions 17

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

The compound interest factor used to determine Present Value in year number 5 is:

Options:

A.

0.3790

B.

0.6209

C.

1.6051

D.

0.6830

Buy Now
Questions 18

______________can be defined as the determination of that course of action or combination of alternatives that yields either the lowest cost or the highest profit.

Options:

A.

Economic optimization

B.

Simulation

C.

Linear programming

D.

Dynamic programming

Buy Now
Questions 19

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

At the end of 30 months, the final price for the piece of equipment will be:

Options:

A.

$328,810

B.

$370,710

C.

$375,658

D.

$378,750

Buy Now
Questions 20

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following methods a used for creating critical path schedules:

Options:

A.

Precedence diagram method

B.

Precedence and arrow diagram methods only

C.

Gantt chart (bar chart) method

D.

Arrow diagram method

Buy Now
Questions 21

The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

9,375 hours have been expended to date. Planned completion at this time is 75%. The project is determined to be 66% complete. Based on current trends, how many hours will be expended at project completion?

Options:

A.

16,215

B.

14,201

C.

12,000

D.

10,526

Buy Now
Questions 22

After collecting the control information on a light rail project within an original budget of 200.0OO work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

After collecting the control information on a light rail project within an original budget of 200.000work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor Is 60%.

Is the percent complete stated by the contractor correct?

Options:

A.

No, it should be 55.0%

B.

No, it should be 50.0%

C.

No, it should be 52.5%

D.

Yes, it is 60%

Buy Now
Questions 23

Which of the following best describes the concept of total cost management:

Options:

A.

A method of quantifying construction damages where the total job costs are subtracted from the original bid or estimate to determine the total cost amount for a claim

B.

The practices and processes utilized to manage the total life cycle cost investment in a portfolio of strategic assets

C.

A job cost system for ensuring all aspects of a particular manufacturing process are accumulated completely

D.

An integrating process that maps the fields of practice of cost engineering without linking it to project management, resource management, or accounting

Buy Now
Questions 24

A concrete slab measuring 10 feet wide by 13.5 feet long by 6 inches deep is to be installed. How many cubic yards of concrete will be required?

Options:

A.

3.0 cubic yards

B.

2.0 cubic yards

C.

3.5 cubic yards

D.

2.5 cubic yards

Buy Now
Questions 25

SCENARIO: A can manufacturing company requested you to provide data for their decision making The unit prices of the can varies but an average selling price of $0.55 cents and average cost of S45 cents is estimated.

The monthly fixed costs are:

Rant-$1,500

Wages - $4.000

Miscellaneous fixed expenses - $500

If there is an additional variable cost of $0.02 per unit, the monthly break even units are:

Options:

A.

40,000 units

B.

48,500 units

C.

75,000 units

D.

60,000 units

Buy Now
Questions 26

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The longest path depends upon relationships driving the timing of activity starts, therefore the following scheduling features should not be used in calculating file longest path.

Options:

A.

milestone activities

B.

activities with lag

C.

activities with short durations

D.

constraints, resource leveling, and interruptible activities

Buy Now
Questions 27

Which of the following is a disadvantage to using target contract as a method of contracting?

Options:

A.

Encourages economic and speedy completion

B.

No opportunity to competitively bid the targets

C.

Almost immediate start on the work, even without scope definition

D.

Flexibility in controlling the work

Buy Now
Questions 28

Which of the following are used for profitability analysis in a construction company?

Options:

A.

Sum of years digits

B.

Return on Investment (ROI) and Rate of Return (ROR)

C.

Opportunity costs

D.

Booked costs

Buy Now
Questions 29

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Activity total slack

B.

Remaining duration

C.

Just-in-time" scheduling

D.

Free float

Buy Now
Questions 30

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of thedesign contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Which of the following percent complete measurement techniques is best suited for long-term non-production accounts (such as overhead accounts)?

Options:

A.

Ratio/level of effort

B.

Start/finish

C.

Units completed

D.

Incremental milestone

Buy Now
Questions 31

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Costs which are independent of the system throughout are:

Options:

A.

no answers ate correct

B.

both fixed and variable costs

C.

variable costs fixed costs

D.

fixed costs

Buy Now
Questions 32

After collecting the control information on a light rail project within an original budget of 200.000 work hours, the construction contractor is ready for their monthly progress meeting with the client.

A total of 100.000 work hours have boon scheduled to date. with 105.000 work hours earned, and 110.000 work hours paid. The stated progress by the contractor is 60%.

How does the project stand?

Options:

A.

Schedule is good, cost is bad

B.

Schedule is good cost is good

C.

Schedule is bad cost is good

D.

Schedule is bad, cost is bad

Buy Now
Questions 33

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

Marketing has determined that XY2 can safely increase their per unit selling price to SO.55. The new break even amount for sales (in units) based on the new contribution margin is:

Options:

A.

40,000 units

B.

6,000 units

C.

50,000 units

D.

60,000 units

Buy Now
Questions 34

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

How much money should be set aside today to have $20,000 available eight (8) years from now if the interest rate is 6% compounded annually?

Options:

A.

$31,875

B.

$12,550

C.

$29,600

D.

$13,515

Buy Now
Questions 35

____________ is the application of total resources ($-workers-supports) and activity durations of the logic diagram.

Options:

A.

Planning

B.

Forecasting

C.

Scheduling

D.

Modeling

Buy Now
Questions 36

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

Which of the following is considered a measure of profitability?

Options:

A.

Rate of return

B.

Annual Dividends

C.

Total assets

D.

Annual sales

Buy Now
Questions 37

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

The following question requires your selection of CCC/CCE Scenario 26(2.5.50.1.2) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

Select the statement that best describes the meaning of the +/-notations associated with an estimate. The actual cost is expected:

Options:

A.

To be exactly the percentages stated

B.

To fall within the percentage range stated

C.

To be higher or lower that the percentages stated

D.

To be outside the percentages stated

Buy Now
Questions 38

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Is a rise in the price level of a good or service, or market basket of goods and/or services.

Options:

A.

escalation

B.

deflation

C.

incremental costs

D.

inflation

Buy Now
Questions 39

The following question requires your selection of CCC/CCE Scenario 4 (2.7.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If steel costs $1800/ton at the end of Year 3, what is the price of steel at the end of Year 4?

Options:

A.

$1890/ton

B.

$1863/ton

C.

$1948/ton

D.

$1836/ton

Buy Now
Questions 40

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If you are scheduled for a $100,000 payment at the end of each year for the next five years, what is the equivalent amount if you were to make a lump sum payment now?

Options:

A.

$162,370

B.

$679,397

C.

$379,100

D.

$500,000

Buy Now
Questions 41

Money is value. Having money when you need it is very important. Money can also be valuable when used wisely by knowing when to spend and when to conserve Also, planning now for future expenses can be a plus to the company rather than a debit.

There are several ways to capitalize money and spending. Basically there is the single payment method that has a compound amount factor and a present worth factor. There is the uniform annual series that has a sinking fund factor, capital recovery factor and also the compound amount factor and present worth factor. At this point, we can assure money is worth 10%.

The following question requires your selection of CCC/CCE Scenario 7 (4.8.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

If $20,000 is invested at the end of each fiscal year for the next 10 years, how much would our total investment be worth assuming the interest is at 10%?

Options:

A.

$289,370

B.

$318,740

C.

$265,798

D.

$420,236

Buy Now
Questions 42

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

When analyzing a precedence diagram schedule, the "backward pass"

Options:

A.

Allows total float to be calculated

B.

Determines the duration of each activity

C.

Calculates the earliest allowable start and finish times for the activities in the schedule

D.

Allows activities to finish as soon as all their 'predecessor' relationships are satisfied

Buy Now
Questions 43

A used concrete pumping truck can be purchased for $125,000. The operation costs are expected to be $65,000 the first year and increase 5% each year thereafter. As a result of the purchase, the company will see an increase in income of $100,000 the first year and 5% more each subsequent year. The company uses straight-line depreciation. The truck will have a useful life of five (5) years and no salvage value. Management would like to see a 10% return on any investment. The company's tax rate is 28%.

Assuming the average life span of a lithium battery is two years and is normally distributed with a standard deviation of two months, what is the probability the battery will last between 20 months and 26 months?

Options:

A.

82%

B.

75%

C.

90%

D.

84%

Buy Now
Questions 44

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

If you buy a lot for $3,000 and sell it for $6,000 at the end of 8 years, what is your annual rate of return?

Options:

A.

10.4%

B.

9.1%

C.

8.3%

D.

9.9%

Buy Now
Questions 45

As the leas cost engineer for the XYZ Services Company, you have been requested to provide pertinent for an equipment rental decision. The unit price of the food stuffs varies, but an average unit selling process has been determined to be $0.50 cents and the average unit acquisition cost is $0.40 cents.

The following revenue and expense relationships are predicted:

How many units are required per month to break even?

Options:

A.

65,000 units

B.

60,000 units

C.

50,000 units

D.

40,000 units

Buy Now
Questions 46

The following question requires your selection of CCC/CCE Scenario 6 (2.7.50.1.3) from the right side of your split screen., using the drop down menu, to reference during your response/choice of responses.

Calculate the weighted average unit cost.

Options:

A.

$46.13

B.

$47.63

C.

$48.35

D.

$48.09

Buy Now
Questions 47

Develop a CPM method considering the below tasks and logical relationships. Use this information to answer the related questions.

What is the late finish date of activity 50?

Options:

A.

Day 47

B.

Day 38

C.

Day 28

D.

Day 37

Buy Now
Questions 48

Meetings require:

Options:

A.

Goals, an agenda, preparation, relevant discussions, support for your actions and to consider the total physical and human setting of the meeting

B.

Goals, an agenda, preparation, conclusions, control and conversations that are relevant

C.

Goals, an agenda, preparation, control, good listening skills and relevant discussions

D.

Goals, an agenda, flipchart, computer projector, laser pointer and consulting with others where appropriate

Buy Now
Questions 49

A major theme park is expanding the existing facility over a five-year period. The design phase will be completed one year after the contract is awarded. Major engineering drawings will be finalized two years after the design contract is awarded and construction will begin three years after the award of the design contract. New, unique ride technology will be used and an estimate will need to be developed to identify these costs that have no historical data.

Fred Fiedler's contingency model suggests that:

Options:

A.

Leadership styles are just the opposite of the managerial grid model

B.

Successful leadership depends upon a good match

C.

between the style of the leader and the demands of the situation

D.

Successful leadership can always be imposed by experienced supervision

E.

A relationship oriented leader described the least preferred worker in an unfavorable light

Buy Now
Questions 50

An agricultural corporation that paid 53% in income tax wanted to build a grain elevator designed to last twenty-five (25) years at a cost of $80,000 with no salvage value. Annual income generated would be $22,500 and annual expenditures were to be $12,000.

Answer the question using a straight line depreciation and a 10% interest rate.

The following question requires your selection of CCC/CCE Scenario 17 (4.2.50.1.1) from the right side of your split screen, using the drop down menu, to reference during your response/choice of responses.

What is the 25 year after tax present worth of this project?

Options:

A.

$13,738

B.

$137,466

C.

$(22,533)

D.

$22,533

Buy Now
Questions 51

A schedule's late dates are calculated during the:

Options:

A.

Loop calculations

B.

Backward pass

C.

Forward pass

D.

Float

Buy Now
Questions 52

Which of the following is NOT a part of the five (5) phases of value engineering?

Options:

A.

Cost reduction

B.

Functional analysis

C.

Creative

D.

Information gathering

Buy Now
Questions 53

An American company plans to acquire a new press machine from a Dutch manufacturer under the following conditions. One question remaining to be answered is the expected amount of capital recovery when salvage is accounted for.

The equivalent value of an investment alternative in today's dollars is referred to as the:

Options:

A.

Break-even point

B.

Rate of return

C.

Net present worm

D.

Future value

Buy Now
Questions 54

The latest allowable end time minus the earliest allowable end time on a schedule activity is referred to as:

Options:

A.

Total float

B.

Remaining duration

C.

Free float

D.

Just-in-time scheduling

Buy Now
Questions 55

A systematic coding structure for organizing and managing scope, assets, cost, resources, work and schedule activity information is a______________.

Options:

A.

Cost breakdown structure

B.

Code of accounts

C.

Cost estimate classification

D.

Schedule identification number

Buy Now
Questions 56

A small hole construction project has a baseline budget of $1,000,000. The project is scheduled to be constructed in 12 months. At the and of the first month, the project data is reported as below:

The following question requires your selection of Scenario 1.4.162 from the right side of your split screen, using the drop down menu, to reference during your response/choice of response.

The budgeted cost work performed is;

Options:

A.

$90,000

B.

$100,000

C.

$95,000

D.

$108,000

Buy Now
Exam Code: CCP
Exam Name: Certified Cost Professional (CCP) Exam
Last Update: Oct 22, 2024
Questions: 189
$56  $159.99
$42  $119.99
$35  $99.99
buy now CCP