Winter Special Sale - Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 575363r9

Welcome To DumpsPedia

PMI-100 Sample Questions Answers

Questions 4

What is the estimate at completion (EAC) if the budget at completion (BAC) is $100, the actual cost (AC) is $50, and the earned value (EV) is $25?

Options:

A.

$50

B.

$100

C.

$125

D.

$175

Buy Now
Questions 5

A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?

Options:

A.

Slack

B.

Float

C.

Lag

D.

Lead

Buy Now
Questions 6

As the project progresses, which of the following is routinely collected from the project activities?

Options:

A.

Communication management activities

B.

Change requests

C.

Configuration verification and audit

D.

Work performance information

Buy Now
Questions 7

Projects that share common outcomes, collective capability, knowledge, or skills are often grouped into a:

Options:

A.

portfolio

B.

program

C.

selection

D.

sub portfolio

Buy Now
Questions 8

Which project document is updated in the Control Stakeholder Engagement process?

Options:

A.

Project reports

B.

Issue log

C.

Lessons learned documentation

D.

Work performance information

Buy Now
Questions 9

Which type of analysis is used to determine the cause and degree of difference between the baseline and actual performance?

Options:

A.

Schedule network analysis

B.

Reserve analysis

C.

Alternative analysis

D.

Variance analysis

Buy Now
Questions 10

Which statement is true about the project management body of knowledge?

Options:

A.

Recognized by every project manager

B.

Constantly evolving

C.

The sum of all knowledge related to project management

D.

A sum of knowledge that should be applied on every project

Buy Now
Questions 11

Which document defines how a project is executed, monitored and controlled, and closed?

Options:

A.

Strategic plan

B.

Project charter

C.

Project management plan

D.

Service level agreement

Buy Now
Questions 12

Lessons learned are created and project resources are released in which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Questions 13

What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is moderate (0.20)?

Options:

A.

0.03

B.

0.06

C.

0.10

D.

0.50

Buy Now
Questions 14

Which process is usually a rapid and cost-effective means of establishing priorities for Plan Risk Responses?

Options:

A.

Identify Risks

B.

Plan Risk Management

C.

Perform Qualitative Risk Analysis

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 15

Which project risk listed in the table below is most likely to occur?

Options:

A.

1

B.

2

C.

3

D.

4

Buy Now
Questions 16

Which tool or technique is required in order to determine the project budget?

Options:

A.

Cost of quality

B.

Historical relationships

C.

Project management software

D.

Forecasting

Buy Now
Questions 17

The following is a network diagram for a project.

What is the critical path for the project?

Options:

A.

A-B-C-F-G-I

B.

A-B-C-F-H-I

C.

A-D-E-F-G-I

D.

A-D-E-F-H-I

Buy Now
Questions 18

Project management processes ensure the:

Options:

A.

alignment with organizational strategy

B.

efficient means to achieve the project objectives

C.

performance of the project team

D.

effective flow of the project throughout its life cycle

Buy Now
Questions 19

Which stakeholder approves a project's result?

Options:

A.

Customer

B.

Sponsor

C.

Seller

D.

Functional manager

Buy Now
Questions 20

Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?

Options:

A.

Two

B.

Four

C.

Five

D.

Twelve

Buy Now
Questions 21

Which enterprise environmental factors may influence Plan Schedule Management?

Options:

A.

Cultural views regarding time schedules and professional and ethical behaviors

B.

Historical information and change control procedures

C.

Risk control procedures and the probability and impact matrix

D.

Resource availability and organizational culture and structure

Buy Now
Questions 22

An intentional activity to modify a nonconforming product or product component is called:

Options:

A.

defect repair

B.

work repair

C.

corrective action

D.

preventive action

Buy Now
Questions 23

Completion of the product scope is measured against the product:

Options:

A.

prototypes

B.

requirements

C.

analyses

D.

benchmarks

Buy Now
Questions 24

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?

Options:

A.

WBS directory

B.

Activity list

C.

WBS

D.

Project schedule

Buy Now
Questions 25

Which item is a cost of conformance?

Options:

A.

Training

B.

Liabilities

C.

Lost business

D.

Scrap

Buy Now
Questions 26

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

5

B.

9

C.

12

D.

14

Buy Now
Questions 27

When a project is undertaken to reduce defects in a product or service, the objective of the project is to create a/an:

Options:

A.

improvement

B.

program

C.

result

D.

portfolio

Buy Now
Questions 28

Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?

Options:

A.

Perform Quality Control

B.

Quality Metrics

C.

Perform Quality Assurance

D.

Plan Quality

Buy Now
Questions 29

Retreating from an actual or potential conflict or postponing the issue to be better prepared or to be resolved by others describes which of the five general techniques for managing conflict?

Options:

A.

Smooth/accommodate

B.

Withdraw/avoid

C.

Compromise/reconcile

D.

Force/direct

Buy Now
Questions 30

Which tool or technique is an examination of industry and specific vendor capabilities?

Options:

A.

Independent estimates

B.

Market research

C.

Analytical techniques

D.

Bidder conferences

Buy Now
Questions 31

Success is measured by benefits realization for a:

Options:

A.

strategic plan

B.

project

C.

portfolio

D.

program

Buy Now
Questions 32

Which process involves determining, documenting, and managing stakeholders' needs and requirements to meet project objectives?

Options:

A.

Collect Requirements

B.

Plan Scope Management

C.

Define Scope

D.

Define Activities

Buy Now
Questions 33

Stakeholder communication requirements should be included as a component of:

Options:

A.

enterprise environmental factors

B.

organizational process assets

C.

the project management plan

D.

the stakeholder register

Buy Now
Questions 34

The purpose of developing a project scope management plan is to:

Options:

A.

Manage the timely completion of the project.

B.

Ensure that the project includes all of the work required.

C.

Make sure the project will satisfy the needs for which it was begun.

D.

Reduce the risk of negative events in the project.

Buy Now
Questions 35

A project manager who communicates to the project team though email is using which type of communication?

Options:

A.

Formal

B.

Informal r

C.

Horizontal

D.

Unofficial

Buy Now
Questions 36

The basis of identification for current or potential problems to support later claims or new procurements is provided by:

Options:

A.

A risk urgency assessment.

B.

The scope baseline.

C.

Work performance information.

D.

Procurement audits.

Buy Now
Questions 37

The following is a network diagram for a project.

The total float for the project is how many days?

Options:

A.

3

B.

5

C.

7

D.

9

Buy Now
Questions 38

A project manager requesting industry groups and consultants to recommend project intervention is relying on:

Options:

A.

Communication models.

B.

Stakeholder participation.

C.

Expert judgment

D.

Enterprise environmental factors.

Buy Now
Questions 39

Which item is an example of personnel assessment?

Options:

A.

Resource calendar

B.

Tight matrix

C.

Team-building activity

D.

Focus group

Buy Now
Questions 40

What is project management?

Options:

A.

A logical grouping of project management inputs, outputs, tools, and techniques

B.

Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements

C.

Launching a process that can result in the authorization of a new project

D.

A formal, approved document that defines how the project is executed, monitored, and controlled

Buy Now
Questions 41

The cost benefit analysis tool is used for creating:

Options:

A.

Pareto charts.

B.

quality metrics.

C.

change requests,

D.

Ishikawa diagrams.

Buy Now
Questions 42

Which process is responsible for monitoring the status of the project and product scope and managing changes to the scope baseline?

Options:

A.

Variance Analysis

B.

Define Scope

C.

Verify Scope

D.

Control Scope

Buy Now
Questions 43

Correlated and contextualized information on how closely the scope is being maintained relative to the scope baseline is contained within:

Options:

A.

project documents updates.

B.

project management plan updates.

C.

change requests.

D.

work performance information.

Buy Now
Questions 44

Progressively elaborating high-level information into detailed plans is performed by the:

Options:

A.

project management office

B.

portfolio manager

C.

program manager

D.

project manager

Buy Now
Questions 45

Which term describes an assessment of correctness?

Options:

A.

Accuracy

B.

Precision

C.

Grade

D.

Quality

Buy Now
Questions 46

One of the key benefits of the Plan Human Resource Management process is that it:

Options:

A.

outlines team selection guidelines and team member responsibilities.

B.

establishes project roles and responsibilities.

C.

improves teamwork, interpersonal skills, and competencies.

D.

provides an accurate appraisal of team member performance.

Buy Now
Questions 47

Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:

Options:

A.

updates.

B.

defect repairs.

C.

preventive actions.

D.

corrective actions.

Buy Now
Questions 48

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

Options:

A.

Efficient

B.

Effective

C.

Push

D.

Pull

Buy Now
Questions 49

Which of the Perform Quality Assurance tools and techniques may enhance the creation of the work breakdown structure (VVBS) to give structure to the decomposition of the scope?

Options:

A.

Activity network diagrams

B.

Affinity diagrams

C.

Matrix diagrams

D.

Interrelationship digraphs

Buy Now
Questions 50

The Project Human Resource Management process that involves confirming human resource availability and obtaining the team necessary to complete project activities is:

Options:

A.

Acquire Project Team.

B.

Plan Human Resource Management.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 51

Risk exists the moment that a project is:

Options:

A.

planned.

B.

conceived.

C.

chartered.

D.

executed.

Buy Now
Questions 52

Which of the following is a project constraint?

Options:

A.

Twenty-five percent staff turnover is expected.

B.

The technology to be used is cutting-edge.

C.

Project leadership may change due to volatile political environment.

D.

The product is needed in 250 days.

Buy Now
Questions 53

The process to ensure that appropriate quality standards and operational definitions are used is:

Options:

A.

Plan Quality.

B.

Perform Quality Assurance.

C.

Perform Quality Control.

D.

Total Quality Management.

Buy Now
Questions 54

What happens to a stakeholder's project influence over time?

Options:

A.

Increases

B.

Decreases

C.

Stays the same

D.

Has no bearing

Buy Now
Questions 55

The process of identifying specific actions to be performed to produce project deliverables is:

Options:

A.

Define Activities.

B.

Create WBS.

C.

Define Scope.

D.

Develop Schedule.

Buy Now
Questions 56

The process of establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule is known as:

Options:

A.

Plan Schedule Management.

B.

Develop Project Charter.

C.

Develop Schedule.

D.

Plan Scope Management.

Buy Now
Questions 57

The number of potential communication channels for a project with 5 stakeholders is:

Options:

A.

10.

B.

12.

C.

20.

D.

24.

Buy Now
Questions 58

Which tool or technique is used to develop the human resource management plan?

Options:

A.

Ground rules

B.

Expert judgment

C.

Team-building activities

D.

Interpersonal skills

Buy Now
Questions 59

An output of the Direct and Manage Project Work process is:

Options:

A.

Deliverables.

B.

Activity lists.

C.

A work breakdown structure.

D.

A scope statement.

Buy Now
Questions 60

Conditions that are not under the control of the project team that influence, direct, or constrain a project are called:

Options:

A.

Enterprise environmental factors

B.

Work performance reports

C.

Organizational process assets

D.

Context diagrams

Buy Now
Questions 61

Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?

Options:

A.

Direct and Manage Project Work

B.

Develop Project Management Plan

C.

Plan Quality Management

D.

Monitor and Control Project Work

Buy Now
Questions 62

A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:

Options:

A.

risk management plan

B.

human resource management plan

C.

scope management plan

D.

procurement management plan

Buy Now
Questions 63

A complete set of concepts, terms, and activities that make up an area of specialization is known as:

Options:

A.

a Knowledge Area

B.

a Process Group

C.

program management

D.

portfolio management

Buy Now
Questions 64

Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?

Options:

A.

Collaboration

B.

Negotiation

C.

Decision making

D.

Influencing

Buy Now
Questions 65

A graphic display of project team members and their reporting relationships is known as a:

Options:

A.

Resource calendar.

B.

Project organization chart.

C.

Resource breakdown structure (RBS).

D.

Responsibility assignment matrix (RAM).

Buy Now
Questions 66

The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?

Options:

A.

Project Communications Management

B.

Project Integration Management

C.

Project Risk Management

D.

Project Scope Management

Buy Now
Questions 67

Which type of contract gives both the seller and the buyer flexibility to deviate from performance with financial incentives?

Options:

A.

Cost Plus Incentive Fee (CPIF)

B.

Fixed Price Incentive Fee (FPIF)

C.

Cost Pius Award Re (CPAF)

D.

Time and Material (T&M)

Buy Now
Questions 68

A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used in which process?

Options:

A.

Identify Risks

B.

Control Risks

C.

Perform Quantitative Risk Analysis

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 69

Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?

Options:

A.

Facilitation techniques

B.

Expert judgment

C.

Analytical techniques

D.

Variance analysis

Buy Now
Questions 70

Which item is a formal proposal to modify any document, deliverable, or baseline?

Options:

A.

Change request

B.

Requirements documentation

C.

Scope baseline

D.

Risk urgency assessment

Buy Now
Questions 71

A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:

Options:

A.

Benchmarking.

B.

Context diagrams.

C.

Brainstorming.

D.

Prototyping.

Buy Now
Questions 72

Configuration identification, configuration status accounting, and configuration verification and audit are all activities in which process?

Options:

A.

Perform Quality Assurance

B.

Direct and Manage Project Work

C.

Monitor and Control Project Work

D.

Perform Integrated Change Control

Buy Now
Questions 73

The definition of when and how often the risk management processes will be performed throughout the project life cycle is included in which risk management plan component?

Options:

A.

Timing

B.

Methodology

C.

Risk categories

D.

Budgeting

Buy Now
Questions 74

In a project, total float measures the:

Options:

A.

Ability to shuffle schedule activities to lessen the duration of the project.

B.

Amount of time an activity can be extended or delayed without altering the project finish date.

C.

Cost expended to restore order to the project schedule after crashing the schedule.

D.

Estimate of the total resources needed for the project after performing a forward pass.

Buy Now
Questions 75

Which grid shows which resources are tied to work packages?

Options:

A.

Work breakdown structure (WBS)

B.

Responsibility assignment matrix (RAM)

C.

Project assignment chart

D.

Personnel assignment matrix

Buy Now
Questions 76

Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a critical EVM metric?

Options:

A.

Cost variance (CV)

B.

Cost performance index (CPI)

C.

Budget at completion (BAC)

D.

Variance at completion (VAC)

Buy Now
Questions 77

Status of deliverables, implementation status for change requests, and forecasted estimates to complete are examples of:

Options:

A.

Earned value management.

B.

Enterprise environmental factors.

C.

Organizational process assets.

D.

Work performance information.

Buy Now
Questions 78

Which tool or technique allows a large number of ideas to be classified into groups for review and analysis?

Options:

A.

Nominal group technique

B.

Idea/mind mapping

C.

Affinity diagram

D.

Brainstorming

Buy Now
Questions 79

Which item is an input to the Define Activities process?

Options:

A.

Schedule data

B.

Activity list

C.

Risk register

D.

Scope baseline

Buy Now
Questions 80

What is the schedule performance index (SPI) if the planned value (PV) is $100, the actual cost (AC) is $150, and the earned value (EV) is $50?

Options:

A.

0.50

B.

0.67

C.

1.50

D.

2.00

Buy Now
Questions 81

What is a hierarchically organized depiction of the identified project risks arranged by risk category?

Options:

A.

Risk register

B.

Risk breakdown structure (RBS)

C.

Risk management plan

D.

Risk category

Buy Now
Questions 82

Which type of managers do composite organizations involve?

Options:

A.

Functional managers and manager of project managers

B.

Functional managers only

C.

Project managers only

D.

Technical managers and project managers

Buy Now
Questions 83

Which Process Group's purpose is to track, review, and regulate the progress and performance of the project; identify any areas in which changes to the plan are required; and initiate the corresponding changes?

Options:

A.

Monitoring and Controlling

B.

Initiating

C.

Planning

D.

Executing

Buy Now
Questions 84

The individual or group that provides resources and support for a project and is accountable for success is the:

Options:

A.

sponsor

B.

customer

C.

business partners

D.

functional managers

Buy Now
Questions 85

Which of the following is the primary output of the Identify Risks process?

Options:

A.

Risk management plan

B.

Risk register

C.

Change requests

D.

Risk response plan

Buy Now
Questions 86

Which Process Group contains those processes performed to define a new project?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Closing

Buy Now
Questions 87

Which defines the portion of work included in a contract for items being purchased or acquired?

Options:

A.

Procurement management plan

B.

Evaluation criteria

C.

Work breakdown structure

D.

Procurement statement of work

Buy Now
Questions 88

In an organization with a projectized organizational structure, who controls the project budget?

Options:

A.

Functional manager

B.

Project manager

C.

Program manager

D.

Project management office

Buy Now
Questions 89

Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?

Options:

A.

Scope audits

B.

Scope reviews

C.

Quality audits

D.

Control chart

Buy Now
Questions 90

Assigned risk ratings are based upon:

Options:

A.

Root cause analysis.

B.

Risk probability and impact assessment.

C.

Expert judgment.

D.

Revised stakeholders' tolerances.

Buy Now
Questions 91

If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?

Options:

A.

One

B.

Five

C.

Six

D.

Seven

Buy Now
Questions 92

Who selects the appropriate processes for a project?

Options:

A.

Project stakeholders

B.

Project sponsor and project stakeholder

C.

Project manager and project team

D.

Project manager and project sponsor

Buy Now
Questions 93

Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?

Options:

A.

Identify Risks

B.

Perform Qualitative Risk Analysis

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 94

Which organizational process assets update is performed during the Close Procurements process?

Options:

A.

Procurement audit

B.

Lessons learned

C.

Performance reporting

D.

Payment requests

Buy Now
Questions 95

Which technique is used in Perform Quantitative Risk Analysis?

Options:

A.

Sensitivity analysis

B.

Probability and impact matrix

C.

Risk data quality assessment

D.

Risk categorization

Buy Now
Questions 96

An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?

Options:

A.

Customer request

B.

Market demand

C.

Technological advance

D.

Strategic opportunity

Buy Now
Questions 97

Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?

Options:

A.

Complete project phase

B.

Project life

C.

The project life cycle

D.

Project cycle

Buy Now
Questions 98

Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?

Options:

A.

Control chart

B.

Earned value

C.

Variance

D.

Trend

Buy Now
Questions 99

Which of the following is an output of the Monitor and Control Project Work process?

Options:

A.

Change requests

B.

Performance reports

C.

Organizational process assets

D.

Project management plan

Buy Now
Questions 100

What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?

Options:

A.

0.45

B.

0.56

C.

0.70

D.

1.36

Buy Now
Questions 101

What is one of the objectives of Project Risk Management?

Options:

A.

Decrease the probability and impact of an event on project objectives.

B.

Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place.

C.

Increase the probability and impact of positive events.

D.

Removal of project risk.

Buy Now
Questions 102

Which of the following techniques is used during Control Scope?

Options:

A.

Cost-benefit analysis

B.

Variance analysis

C.

Reserve analysis

D.

Stakeholder analysis

Buy Now
Questions 103

Which is an example of Administer Procurements?

Options:

A.

Negotiating the contract

B.

Authorizing contractor work

C.

Developing the statement of work

D.

Establishing evaluation criteria

Buy Now
Questions 104

Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?

Options:

A.

Analogous

B.

Parametric

C.

Bottom-up

D.

Top-down

Buy Now
Questions 105

The Define Scope process is in which of the following Process Groups?

Options:

A.

Initiating

B.

Planning

C.

Monitoring and Controlling

D.

Executing

Buy Now
Questions 106

The scope of a project cannot be defined without some basic understanding of how to create the specified:

Options:

A.

objectives

B.

schedule

C.

product

D.

approach

Buy Now
Questions 107

Definitions of probability and impact, revised stakeholder tolerances, and tracking are components of which subsidiary plan?

Options:

A.

Cost management plan

B.

Quality management plan

C.

Communications management plan

D.

Risk management plan

Buy Now
Questions 108

An input of the Plan Procurement Management process is:

Options:

A.

Make-or-buy decisions.

B.

Activity cost estimates.

C.

Seller proposals.

D.

Procurement documents.

Buy Now
Questions 109

Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?

Options:

A.

The Delphi technique

B.

Nominal group technique

C.

Affinity diagram

D.

Brainstorming

Buy Now
Questions 110

The stakeholder register is an output of:

Options:

A.

Identify Stakeholders.

B.

Plan Stakeholder Management.

C.

Control Stakeholder Engagement.

D.

Manage Stakeholder Engagement.

Buy Now
Questions 111

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

Options:

A.

Finish-to-start planning

B.

Rolling wave planning

C.

Short term planning

D.

Dependency determination

Buy Now
Questions 112

The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:

Options:

A.

Collect Requirements.

B.

Conduct Procurements.

C.

Estimate Activity Durations.

D.

Estimate Activity Resources.

Buy Now
Questions 113

The Plan Stakeholder Management process belongs to which Process Group?

Options:

A.

Executing

B.

Initiating

C.

Planning

D.

Monitoring and Controlling

Buy Now
Questions 114

When should quality planning be performed?

Options:

A.

While developing the project charter

B.

In parallel with the other planning processes

C.

As part of a detailed risk analysis

D.

As a separate step from the other planning processes

Buy Now
Questions 115

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

Options:

A.

Plan Human Resource Management.

B.

Acquire Project Team.

C.

Manage Project Team.

D.

Develop Project Team.

Buy Now
Questions 116

The planned work contained in the lowest level of work breakdown structure (WBS) components is known as:

Options:

A.

Work packages.

B.

Accepted deliverables.

C.

The WBS dictionary.

D.

The scope baseline.

Buy Now
Questions 117

The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:

Options:

A.

Continuous improvement.

B.

Predictive planning.

C.

Progressive elaboration.

D.

Quality assurance.

Buy Now
Questions 118

Which tool or technique is used to manage change requests and the resulting decisions?

Options:

A.

Change control tools

B.

Expert judgment

C.

Delphi technique

D.

Change log

Buy Now
Questions 119

Units of measure, level of precision, level of accuracy, control thresholds, and rules of performance measurement are examples of items that are established in the:

Options:

A.

Cost management plan.

B.

Work performance information.

C.

Quality management plan.

D.

Work breakdown structure.

Buy Now
Questions 120

An output of the Manage Stakeholder Engagement process is:

Options:

A.

change requests

B.

enterprise environmental factors

C.

the stakeholder management plan

D.

the change log

Buy Now
Questions 121

Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?

Options:

A.

Develop Project Management Plan

B.

Develop Project Charter

C.

Direct and Manage Project Execution

D.

Collect Requirements

Buy Now
Questions 122

The procurement process that documents agreements and related documentation for future reference is known as:

Options:

A.

Plan Procurements.

B.

Control Procurements.

C.

Close Procurements.

D.

Conduct Procurements.

Buy Now
Questions 123

Which items are an output of the Perform Integrated Change Control process?

Options:

A.

Work performance reports

B.

Accepted deliverables

C.

Project management plan updates

D.

Organizational process assets

Buy Now
Questions 124

Those who enter into a contractual agreement to provide services necessary for a project are:

Options:

A.

buyers

B.

sellers

C.

business partners

D.

product users

Buy Now
Questions 125

Which process is conducted from project inception through completion and is ultimately the responsibility of the project manager?

Options:

A.

Control Quality

B.

Monitor and Control Project Work

C.

Control Scope

D.

Perform Integrated Change Control

Buy Now
Questions 126

Which Manage Communications tool or technique focuses on identifying and managing barriers?

Options:

A.

Communication methods

B.

Information technology

C.

Communication models

D.

Information management systems

Buy Now
Questions 127

The purpose of the Project Communications Management Knowledge Area is to:

Options:

A.

Monitor and control communications throughout the entire project life cycle.

B.

Maintain an optimal flow of information among all project participants.

C.

Develop an appropriate approach for project communications.

D.

Ensure timely and appropriate collection of project information.

Buy Now
Questions 128

Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?

Options:

A.

Stakeholder register

B.

Scope management plan

C.

Stakeholder management plan

D.

Project charter

Buy Now
Questions 129

The Monitoring and Controlling Process Group includes processes that:

Options:

A.

Establish the scope, objectives, and course of action of a project,

B.

Define a new project or a new phase of an existing project.

C.

Track, review, and regulate the progress and performance of a project.

D.

Complete the work defined in the project management plan.

Buy Now
Questions 130

Which Knowledge Areas include processes from the Closing Process Group?

Options:

A.

Project Quality Management and Project Time Management

B.

Project Scope Management and Project Risk Management

C.

Project Stakeholder Management and Project Cost Management

D.

Project Integration Management and Project Procurement Management

Buy Now
Questions 131

An output of the Develop Project Team process is:

Options:

A.

Organizational process assets.

B.

Enterprise environmental factors updates.

C.

Project staff assignments.

D.

Organizational charts and position descriptions.

Buy Now
Questions 132

Identify Risks is part of which Process Group?

Options:

A.

Planning

B.

Executing

C.

Closing

D.

Initiating

Buy Now
Questions 133

Processes in the Planning Process Group are typically carried out during which part of the project life cycle?

Options:

A.

Only once, at the beginning

B.

At the beginning and the end

C.

Once during each phase

D.

Repeatedly

Buy Now
Questions 134

Which schedule method allows the project team to place buffers on the project schedule path to account for limited resources and project uncertainties?

Options:

A.

Critical path method

B.

Critical chain method

C.

Resource leveling

D.

Schedule network analysis

Buy Now
Questions 135

Which items are components of a project management plan?

Options:

A.

Change management plan, process improvement plan, and scope management plan

B.

Agreements, procurement management plan, and work performance information

C.

Schedule management plan, project schedule, and resource calendars

D.

Scope baseline, project statement of work, and requirements traceability matrix

Buy Now
Questions 136

A collection of projects managed as a group to achieve strategic objectives is referred to as a:

Options:

A.

plan

B.

process

C.

program

D.

portfolio

Buy Now
Questions 137

Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?

Options:

A.

Histograms

B.

Scatter diagrams

C.

Flowcharts

D.

Checksheets

Buy Now
Questions 138

An input required in Define Scope is an organizational:

Options:

A.

structure.

B.

process asset.

C.

matrix.

D.

breakdown structure.

Buy Now
Questions 139

Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?

Options:

A.

Work breakdown structure

B.

Organizational breakdown structure

C.

Resource breakdown structure

D.

Bill of materials

Buy Now
Questions 140

Which of the following involves making information available to project stakeholders in a timely manner?

Options:

A.

Plan Communications

B.

Performance reporting

C.

Project status reports

D.

Distribute Information

Buy Now
Questions 141

Which of the following is an output of the Define Activities process?

Options:

A.

Activity list

B.

Project plan

C.

Activity duration estimates

D.

Project schedule

Buy Now
Questions 142

Which process involves aggregating the estimated costs of the individual schedule activities or work packages?

Options:

A.

Estimate Costs

B.

Estimate Activity Resources

C.

Control Costs

D.

Determine Budget

Buy Now
Questions 143

What is the function of a Project Management Office (PMO)?

Options:

A.

To focus on the coordinated planning, prioritization, and execution of projects and subprojects that are tied to the parent organizations or the client's overall business objectives.

B.

To coordinate and manage the procurement of projects relevant to the parent organization's business objectives and to administer the project charters accordingly.

C.

To administer performance reviews for the project manager and the project team members and to handle any personnel and payroll issues.

D.

To focus on the specified project objectives and to manage the scope, schedule, cost, and quality of the work packages.

Buy Now
Questions 144

Which document includes the project scope, major deliverables, assumptions, and constraints?

Options:

A.

Project charter

B.

Project scope statement

C.

Scope management plan

D.

Project document updates

Buy Now
Questions 145

Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?

Options:

A.

Resource breakdown structure

B.

Staffing management plan

C.

Project organizational chart

D.

Scope management plan

Buy Now
Questions 146

What is the name of a graphic display of project team members and their reporting relationships?

Options:

A.

Role dependencies chart

B.

Reporting flow diagram

C.

Project organization chart

D.

Project team structure diagram

Buy Now
Questions 147

A project management office manages a number of aspects including the:

Options:

A.

Project scope, schedule, cost, and quality of the products of the work packages.

B.

Central coordination of communication management across projects.

C.

Assignment of project resources to best meet project objectives.

D.

Overall risk, overall opportunity, and interdependencies among projects at the enterprise level.

Buy Now
Questions 148

A tool or technique in Perform Quality Control that a project manager would use is:

Options:

A.

quality audits.

B.

process analysis.

C.

benchmarking.

D.

inspection.

Buy Now
Questions 149

Co-location is a tool and technique of:

Options:

A.

Develop Human Resource Plan.

B.

Manage Project Team.

C.

Develop Project Team.

D.

Acquire Project Team.

Buy Now
Questions 150

Which type of chart is a graphic representation of a process showing the relationships among process steps?

Options:

A.

Control

B.

Bar

C.

Flow

D.

Pareto

Buy Now
Questions 151

Which activity involves ensuring that the composition of a projects configuration items is correct?

Options:

A.

Configuration Identification

B.

Configuration Status Accounting

C.

Configuration Verification and Audit

D.

Configuration Quality Assurance

Buy Now
Questions 152

Which of the following Project Communication Management processes uses performance reports as an input?

Options:

A.

Manage Stakeholder Expectations

B.

Report Performance

C.

Distribute Information

D.

Plan Communications

Buy Now
Questions 153

Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?

Options:

A.

Perform Quality Control

B.

Perform Quality Assurance

C.

Plan Quality

D.

Report Performance

Buy Now
Questions 154

The key benefit of the Monitoring and Controlling Process Group is the ability to:

Options:

A.

establish and manage project communication channels, both external and internal to the project team.

B.

influence the stakeholders that want to circumvent integrated change control so that their changes are implemented.

C.

monitor the ongoing project team against the team performance assessments and the project performance baseline.

D.

observe and measure project performance regularly and consistently to identify variances from the project management plan.

Buy Now
Questions 155

What provides information regarding the ways people, teams, and organizational units behave?

Options:

A.

Organizational chart

B.

Organizational theory

C.

Organizational structure

D.

Organizational behavior

Buy Now
Questions 156

How many Project Management Process Groups are there?

Options:

A.

3

B.

4

C.

5

D.

6

Buy Now
Questions 157

During which process would stakeholders provide formal acceptance of the completed project scope?

Options:

A.

Perform Quality Control

B.

Verify Scope

C.

Control Scope

D.

Develop Schedule

Buy Now
Questions 158

To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:

Options:

A.

scope creep.

B.

a change request.

C.

work performance information.

D.

deliverables.

Buy Now
Questions 159

When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:

Options:

A.

divided among each of the phases or subprojects.

B.

repeated for each of the phases or subprojects.

C.

linked to specific phases or subprojects.

D.

integrated for specific phases or subprojects.

Buy Now
Questions 160

The process of identifying the stakeholders' information needs is completed during:

Options:

A.

Plan Communications.

B.

Manage Stakeholder Expectations.

C.

Stakeholder Analysis.

D.

Identify Stakeholders.

Buy Now
Questions 161

In which process is a project manager identified and given the authority to apply resources to project activities?

Options:

A.

Acquire Project Team

B.

Develop Project Management Plan

C.

Manage Project Execution

D.

Develop Project Charter

Buy Now
Questions 162

What does a CPI value greater than 1.0 indicate?

Options:

A.

Cost right at the estimated value

B.

Cost under the estimated value

C.

Cost right at the actual value

D.

Cost over the estimated value

Buy Now
Questions 163

The precedence diagramming method (PDM) is also known as:

Options:

A.

Arrow Diagram.

B.

Critical Path Methodology (CPM).

C.

Activity-On-Node (AON).

D.

schedule network diagram.

Buy Now
Questions 164

Which process determines the risks that might affect the project?

Options:

A.

Perform Qualitative Risk Analysis

B.

Identify Risks

C.

Plan Risk Management

D.

Perform Quantitative Risk Analysis

Buy Now
Questions 165

Quality metrics are an output of which process?

Options:

A.

Plan Quality

B.

Perform Quality Control

C.

Perform Quality Assurance

D.

Perform Qualitative Risk Analysis

Buy Now
Questions 166

Testing falls into which of the following categories of cost of quality?

Options:

A.

Internal failure costs

B.

Prevention costs

C.

Appraisal costs

D.

External failure costs

Buy Now
Questions 167

Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?

Options:

A.

Exploit

B.

Share

C.

Enhance

D.

Transfer

Buy Now
Questions 168

Which of the following is an information gathering technique in Identify Risks?

Options:

A.

Influence diagrams

B.

Brainstorming

C.

Assumption analysis

D.

SWOT analysis

Buy Now
Questions 169

Which of the following factors is lowest at the start of the project?

Options:

A.

Cost of changes

B.

Stakeholder influences

C.

Risk

D.

Uncertainty

Buy Now
Questions 170

Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?

Options:

A.

Project Plan

B.

Responsibility Matrix

C.

Issue Log

D.

Scope Document

Buy Now
Questions 171

Monte Carlo is which type of risk analysis technique?

Options:

A.

Probability

B.

Quantitative

C.

Qualitative

D.

Sensitivity

Buy Now
Questions 172

Which of the following reduces the probability of potential consequences of project risk events?

Options:

A.

Preventive action

B.

Risk management

C.

Corrective action

D.

Defect repair

Buy Now
Questions 173

The project manager needs to review the templates in use. The templates are part of the:

Options:

A.

Enterprise environmental factors.

B.

Historical information,

C.

Organizational process assets.

D.

Corporate knowledge base.

Buy Now
Questions 174

When sequencing activities, what does the common acronym FF stand for?

Options:

A.

Fixed Fee

B.

Free Float

C.

Fixed Finish

D.

Finish-to-Finish

Buy Now
Questions 175

Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?

Options:

A.

Compromising

B.

Collaborating

C.

Smoothing

D.

Problem Solving

Buy Now
Questions 176

Which of the following characteristics are found in a functional organizational structure?

Options:

A.

Little or no project manager authority, little or no resource availability, and the functional manager controls the project budget

B.

Limited project manager authority, limited resource availability, and a part-time project manager's role

C.

Low to moderate project manager authority, low to moderate resource availability, and a full-time project manager's role

D.

High to almost total project manager authority, high to almost total resource availability, and full-time project management administrative staff

Buy Now
Questions 177

What risk technique is used to quantify the probability and impact of risks on project objectives?

Options:

A.

Expert judgment

B.

Risk registry

C.

Risk response planning

D.

Interviewing

Buy Now
Questions 178

A method to manage stakeholder expectations in the scope statement is to clearly:

Options:

A.

state the guiding principles of the organization.

B.

identify alternatives to generate different approaches.

C.

state what is out of scope.

D.

outline the results of the Delphi technique.

Buy Now
Questions 179

The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:

Options:

A.

Executing.

B.

Initiating,

C.

Monitoring and Controlling.

D.

Planning.

Buy Now
Questions 180

Which of the following types of a dependency determination is used to define the sequence of activities?

Options:

A.

Legal

B.

Discretionary

C.

Internal

D.

Resource

Buy Now
Questions 181

Change request status updates are an output of which process?

Options:

A.

Perform Integrated Change Control

B.

Direct and Manage Project Execution

C.

Close Project or Phase

D.

Monitor and Control Project Work

Buy Now
Questions 182

In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?

Options:

A.

Team meetings

B.

Subcontracting teams

C.

Virtual teams

D.

Teamwork

Buy Now
Questions 183

Which process should be conducted from the project inception through completion?

Options:

A.

Monitor and Control Project Work

B.

Perform Quality Control

C.

Perform Integrated Change Control

D.

Monitor and Control Risks

Buy Now
Questions 184

Which of the following is an example of the simplest fixed-price contract?

Options:

A.

Purchase requisition

B.

Purchase order

C.

Verbal agreement

D.

Request for quote

Buy Now
Questions 185

The process improvement plan details the steps for analyzing processes to identify activities which enhance their:

Options:

A.

quality.

B.

value.

C.

technical performance.

D.

status.

Buy Now
Questions 186

The correct equation for schedule variance (SV) is earned value:

Options:

A.

minus planned value [EV - PV].

B.

minus actual cost [EV - AC].

C.

divided by planned value [EV/PV],

D.

divided by actual cost [EV/AC].

Buy Now
Questions 187

A project lifecycle is defined as:

Options:

A.

a collection of generally sequential and sometimes overlapping project phases.

B.

a process required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.

C.

a recognized standard for the project management profession.

D.

the application of knowledge, skills, tools, and techniques to project activities to meet the project requirements.

Buy Now
Questions 188

Who determines which dependencies are mandatory during the Sequence Activities process?

Options:

A.

Project manager

B.

External stakeholders

C.

Internal stakeholders

D.

Project team

Buy Now
Questions 189

Which of the following are an enterprise environmental factor that can influence the Identify Risks process?

Options:

A.

Work performance reports

B.

Assumptions logs

C.

Network diagrams

D.

Academic studies

Buy Now
Questions 190

The process for performing variance analysis may vary, depending on:

Options:

A.

scenario building, technology forecasting, and forecast by analogy.

B.

working relationships among various stakeholders and team members.

C.

application area, the standard used, and the industry,

D.

work to be completed next.

Buy Now
Questions 191

Which characteristics do effective project managers possess?

Options:

A.

Project management knowledge, performance skills, and personal effectiveness

B.

Preparedness, project management knowledge, and personality characteristics

C.

General management, preparedness, and project management knowledge

D.

Assertiveness, collaboration, and performance skills

Buy Now
Questions 192

Under which type of contract does the seller receive reimbursement for all allowable costs for performing contract work, as well as a fixed-fee payment calculated as a percentage of the initial estimated project costs?

Options:

A.

Cost Plus Fixed Fee Contract (CPFF)

B.

Cost Plus Incentive Fee Contract (CPIF)

C.

Firm Fixed Price Contract (FFP)

D.

Fixed Price with Economic Price Adjustment Contract (FP-EPA)

Buy Now
Questions 193

The completion of the project scope is measured against the:

Options:

A.

requirements documentation.

B.

project scope statement.

C.

project management plan.

D.

work performance measurements.

Buy Now
Questions 194

In Plan Risk Management, which of the management plans determines who will be available to share information on various risks and responses at different times and locations?

Options:

A.

Schedule

B.

Quality

C.

Communications

D.

Cost

Buy Now
Questions 195

The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:

Options:

A.

operate separately.

B.

move together in batches,

C.

overlap and interact.

D.

move in a sequence.

Buy Now
Questions 196

Plan-do-check-act is also known as:

Options:

A.

prevention over inspection.

B.

statistical sampling.

C.

management responsibility,

D.

continuous improvement.

Buy Now
Questions 197

The total of the planned value (PV) is also known as:

Options:

A.

work breakdown structure (WBS).

B.

schedule target.

C.

performance measurement baseline (PMB).

D.

earned value baseline.

Buy Now
Questions 198

The processes required to establish the scope of the project, refine the objectives, and define the course of action required to attain the objectives that the project has been undertaken to achieve are grouped within which Process Group?

Options:

A.

Initiating

B.

Planning

C.

Executing

D.

Monitoring and Controlling

Buy Now
Questions 199

Who is responsible for initiating a project?

Options:

A.

Project sponsor

B.

Project manager

C.

Program manager

D.

Project management office (PMO)

Buy Now
Questions 200

The initial development of a Project Scope Management plan uses which technique?

Options:

A.

Alternatives identification

B.

Scope decomposition

C.

Expert judgment

D.

Product analysis

Buy Now
Questions 201

Which of the following are three inputs to the risk register?

Options:

A.

Risk register updates, stakeholder register, and quality management plan

B.

Communication management plan, enterprise environmental factors, and activity duration estimates

C.

Risk management plan, activity cost estimates, and project documents

D.

Project scope statement, organizational process assets, and scope baseline

Buy Now
Questions 202

Resource calendars are included in the:

Options:

A.

staffing management plan.

B.

work breakdown structure (WBS).

C.

project communications plan.

D.

project charter.

Buy Now
Questions 203

Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?

Options:

A.

The risk of achieving the shortened project time is increased.

B.

The critical path will have positive total float.

C.

Contingency reserves are released for redeployment by the project manager.

D.

Duration buffers are added to maintain a focus on planned activity durations.

Buy Now
Questions 204

Activity cost estimates are quantitative assessments of the probable costs required to:

Options:

A.

Create WBS.

B.

complete project work.

C.

calculate costs.

D.

Develop Project Management Plan.

Buy Now
Questions 205

Funding limit reconciliation is a tool and technique used in which process?

Options:

A.

Control Costs

B.

Determine Budget

C.

Estimate Costs

D.

Control Budget

Buy Now
Questions 206

Which of the following is a strategy to deal with positive risks or opportunities?

Options:

A.

Mitigate

B.

Transfer

C.

Exploit

D.

Avoid

Buy Now
Questions 207

Which index is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal?

Options:

A.

Estimate at completion

B.

Cost performance

C.

Schedule performance

D.

To-complete performance

Buy Now
Questions 208

Expected monetary value (EMV) is computed by which equation?

Options:

A.

Value of each possible outcome multiplied by probability of occurrence

B.

Value of each possible outcome multiplied by probability of non-occurrence

C.

Multiplying the value of each possible outcome by the probability of occurrence and adding the products together

D.

Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together

Buy Now
Questions 209

The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:

Options:

A.

majority rule technique.

B.

nominal group technique.

C.

Delphi technique,

D.

idea/mind mapping technique.

Buy Now
Questions 210

Which of the following is an estimating technique that uses the values of parameters from previous similar projects for estimating the same parameter or measure for a current project?

Options:

A.

Reserve analysis

B.

Three-point estimating

C.

Parametric estimating

D.

Analogous estimating

Buy Now
Questions 211

In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?

Options:

A.

Firm-Fixed-Price (FFP)

B.

Fixed Price with Economic Price Adjustments (FP-EPA)

C.

Fixed-Price-Incentive-Fee (FPIF)

D.

Cost Plus Fixed Fee (CPFF)

Buy Now
Exam Code: PMI-100
Exam Name: Certified Associate in Project Management (CAPM)®
Last Update: Nov 29, 2024
Questions: 704
$66  $164.99
$50  $124.99
$42  $104.99
buy now PMI-100