In specifying labels and pruned tags that meet Underwriters Laboratories (UL) 969 Standard, marking and labeling systems are provided following the listed metrics. Which two of the following are REQUIRED for the UL standard? (Select two options.)
A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board.
What should the program manager do next?
When designing for horizontal pathways in an environment that requires fire-stopping for penetrating a rated wall, what is the MAXIMUM till ratio for telecommunications cabling in a cable tray?
A program manager is working on benefits. The program team created and updated a benefits register earlier in the program. The benefits register should include which of the following?
A program manager needs to establish direction and identity the essential aspects of a program. In addition, they must ensure that the context and framework of the program are properly defined assessed and documented
Which document will be created to support this activity?
For a cost estimate, an ICT distribution designer should produce a document listing each task with a cost placed beside them. The type of document used is a
What's the RECOMMENDED twisted pair cable slack length to be left at the work area outlet location to enable the possibility of future changes in the Horizontal Cabling System?
Stakeholders make ad-hoc requests on a routine basis. This causes duplication of reporting and communication gaps that affect the program's performance
To resolve this situation, which of the following must go through critical review and change"?
A program manager is developing a program management plan by integrating the plans of constituent projects. During this effort, the program manager learns that a resource is critical to more than one component and there is a time overlap for their availability
When creating the program resource management plan, what should the program manager do first?
A program manager recognizes that a successful resource being used in project A could also be used in project B. What should the program manager do first to leverage the utilization of this resource?
An ICT distribution designer is estimating the installation of five units of 1.5 m (5 ft) tong channel basket trays connected together in the ceiling. The total length of the pathway needed is 7 5 m (25 ft). How many supports will be needed''
66-style connecting blocks (certain designs) can support up to what category of transmission performance?
A key stakeholder's requirement contradicts the organization's strategic objectives. The program manager meets with the stakeholder but is unable to reach a compromise on the requirement
What should the program manager do first?
A program sponsor is concerned about the status of high-priority risks and budget variances. The program manager should refer lo which of the following?
What is the MAXIMUM number of work areas served by a single Multiuser Telecommunications Outlet Assembly (MUTOA)?
Program A is dependent upon program B lo complete benefits sustainment for two benefits Program A is on track to meet program benefits However program B's program manager has just advised that program B has been closed.
What should program A's program manager update and review first with the stakeholders?
How does a portfolio’s collection of work differ from that of a program's collection of work?
An organization must accelerate a product to market. The program manager completes the preliminary program slaps and holds a kick-off meeting Project managers submit their preliminary schedules for review
What should the program manager do next?
Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new product. In a meeting with Company B, you determine that additional funding will be required and resources allocated and scheduled
What is your MOST appropriate next step?
What's the MINIMUM depth of a trench from top of the cable/conduit to final grade? (Select two options.)
The program manager defines the program objectives, requirements and develops a high-level road map. To ensure program alignment with the enterprise strategic plan the program manager should work with which of the following?
Using an earth ground resistance tester, what is the recommended MAXIMUM value for resistance between any two points along the entire length of a bonding or grounding conductor (not including the earth electrode system)?
Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another
How should the program manager decide which template is appropriate?
A component protect of a multiyear program delivers all expected products and services as anticipated. The component project manager obtains approvals from the stakeholders and transitions the benefits to operations
What should the program manager do next?
A global financial system is being delivered by the program learn to allow access from anywhere in the world Following a new cross-border regulation applying to privacy of local banking data accessed from abroad, the CEO of the bank requests that an external audit be conducted lo validate compliance with this new regulation. This event, which was not anticipated al this phase of the program, will generate additional work tor the program learn. This effort Is not included in the current program roadmap and benefits delivery plan
What immediate actions should the program manager take?
Which two of the following types of metallic conduit REQUIRE threaded couplings? (Select two options.)
A new component project is approved by the program governance board. The funding for this component project will be provided by an organization different from the organization funding the program
Would this be an acceptable funding arrangement?
An unforeseen geopolitical risk impacts a program to establish a company's operations abroad. Stakeholders now want to establish a risk response team to define a mitigation plan. Ultimately what appeared to be a significant risk resulted in a negligible risk.
What should the program manager recommend to stakeholders for future similar situations?
A program manager prepares the program for review to secure funding by senior management. Which of the following must the program manager identify when creating the program charter?
Smaller buildings with a serving area larger than 1000 ft2 and less than 5000 ft2 may be served by:
The project managers for component projects A and B schedule the same resource to perform tasks during the same timeframe, resulting in an over-allocation. The program manager reviews the program resource management plan determine that project. A can wait until the resource becomes available, and assigns the resource to project B.
This is an example of which of the following?
A two-year program is coming to an end Many of the initial governance board members have moved from their current posts or left the company Several new members have joined but have a shod association with the program, which changes the board's expectations and focus. During the final phase gate review, some board members are uncertain of their roles and expectations in the process.
How should the program manager handle this situation?
Exhibit:
A pay telephone using coins needs to be installed in a public area. In the specifications, it is required that the telephone shall meet the ADA (Americans with Disability Act) requirement for side reach using a wheelchair. What will be the maximum reachable height or the value of "X"?
The number of emerging risks increases in a component project and the program manager tails behind in reviewing) and approving the plans. This Impacts the component project manager's ability to effectively address the risks.
In this situation, what should the program manager change about the risk management plan?
Based on the estimated work area size, what is the MAXIMUM number of work areas that a telecommunications enclosure shall serve?
A small regional utility closes a customer rewards program and transitions it to operations The executive sponsor and program manager are concerned about the impact on benefits realization The program manager assures the executive sponsor that any corrective actions will be included in the next phase.
What should the program manager do to ensure a successful transition?
A critical program for a company fails lo delivers its intended benefits. The CEO and program sponsor are both held accountable and. ultimately, their employment is terminated by the board of directors
What should the program manager do before formally closing the program?
What is the MINIMUM distance from the edge of a pool or other water hazards for a weatherproof enclosure?
Which two of the following roles do an ICT distribution designer use to ensure a timely and cost-effective telecommunications construction project? (Select two options.)
In new construction, what is the percentage of pay phones that must be equipped with volume controls?
Which of the following transmitter light sources has a MINIMUM bandwidth of 4700 MHz/km (EMB) at 850 nm">
A voice over IP network that converges voice capabilities with softphones. Video communications, instant messaging is referred to as
A program manager is assigned to a large cross-functional program trial includes five different technologies and multiple workstreams.
Some potential stakeholders have conflicting program expectations
What should the program manager do next/?
A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
In a contiguous properly environment (e. g., where campus backbone cables exist), which two of the following are CRITICAL factors to understand for maintenance and growth purposes? (Select two options.)
A program manager joins a team during its preparation phase. What should the program manager do lo obtain formal sponsor approval to begin the benefits delivery phase1?
Develop the program management plan based on the organization's strategic plan
D. Write the program charter, including the program mission statement and stakeholder engagement plan
C. Define a high-level program roadmap of milestones and schedules supported by a preliminary estimate
D. Identify and document the anticipated program benefits in the benefits management plan.
In preparation for the development and submission of the program master schedule to a client, the program manager meets with (he component project manager and master program scheduler to discuss the work breakdown structure (WBS) During the meeting, the master scheduler indicates that the master program schedule should include which of the following?
A utility company manages its capital improvement projects (CIP) using engineers, project managers, and program managers. A new sponsor from the utility company assesses the CIP and decides to reorganize it into a program. They invite seven companies to discuss their approach to monitor and control the program and its constituent protects.
Where should the program manager incorporate this input?
An ICT distribution designer is representing a client during a project execution. What is the designer's role in the Vendor and Contractor Coordination?
A program manager building the world's largest cruise ship is resolving the conflict between the two main sponsors who cannot agree on the number of food and beverage outlets to have onboard. What should the program manager do?
Identify the fibers below as either single mode (SM) or multi-mode (MM) by dragging the appropriate term into each oval.
When designing horizontal pathways, the ICT distribution designer should consider the design's ability to (Select two options.)
For a six story building (plus a basement) each of the six floors has a useable area of =3716 m2 (40.000 ft2) There are two riser systems, each serving halt of the useable area on each Moor What are the sleeves quantity and configuration required from fifth floor to sixth floor?
Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly. Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)
A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository tor similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity
What should the program manager do with the knowledge gained from this activity?
A company wants to perform a preliminary stakeholder analysis lo assess a new program's support. What should the program manager develop'?
Which of the following statements Is CORRECT concerning best practice for horizontal cable management panels?
An Ethernet passive optical network (EPON) uses an aggregation device called an optical line terminal (OLT). An OLT can support a MINIMUM of______subscribers per port using a passive optical splitter
A program is in its execution phase when a component project manager suggests a potential change that could increase the financial benefit of the program. The program manager is hesitant to submit a change request, as it would extend the program schedule and require a scope change.
To whom should the change request be presented?
What is used to facilitate MINOR changes to the Project Requirements?
Request lot Information (RFI)
A company CEO meets with key customers to learn how they can be better served Alter discovering that some executive team members disagree with each other, the CEO asks the program management office (PWO) to develop a program to better serve key customers based on their strategic importance to the company's long-term goals.
What should the program manager do to establish and successfully manage the program's direction?
A component project manager escalates an issue regarding a key stakeholder to the program manager. The key stakeholder does not respond to emails or phone calls and the project manager believes this key stakeholder is exhibiting a negative attitude toward the work. The key stakeholder has a significant influence over the component project which could impact other components if delays occur. The program manager's attempts to reach the stakeholder via email also fail.
What should the program manager do next?
The program manager plans to address a negative cost variance generating a red flag in the program management status report. What should the program manager do?
Status information, including program and component status, cost information, risk analysis and other relevant information, is provided in which of the following?
The transfer of unwanted signals may occur over one path or several paths. What method addresses the mitigation or suppression of unwanted signals?
Which requirement does the ICT distribution designer provide to the Mechanical Engineer in charge of the HVAC design for a Telecommunication Space?
Which of the following is the process of limiting fire and smoke using fire-resistive barriers?
An ICT distribution designer is coordinating with local agencies for an upcoming campus improvement project which could affect the design. Which two of the following listed items will MINIMIZE design changes once the project begins? (Choose two.)
The program manager compiles a program performance report for review by the program governance board. The performance report indicates that the scope, quality and schedule objectives have been me, but costs and resource utilization are higher than expected The program can no longer deliver the planned return-on-investment within an acceptable level and the intended benefits have not yet been realized
After further analysis of the performance indicators the program manager should do which of the following*?
Which two of the following are included in the ICT distribution designer's role of vendor and contractor coordination'? (Select two options.)
A program manager has been assigned to a program that has received approval of the program charter and for which a stakeholder register has been prepared. During stakeholder engagement planning the program manager should consider which of the following stakeholder aspects?
When sizing an underground entrance facility, what is the MINIMUM amount of 103 metric designator conduits (4 trade size) that should be specified by the ICT distribution design?
A component is scheduled to close at the end of the week. What should the program manager verity prior to allowing the component to close?
A program is midway through the program delivery phase when a key stakeholder asks if the program is meeting its defined objectives.
How should the program manager demonstrate the program's progress"?
A program governance board mandates that phase gate reviews must be held so each component project can be reviewed and individually authorized to proceed to the next phase Tracking and reporting of actual benefits realized is one part of the review
What is the other part of the review"?
An ICT distribution designer is reviewing a client's site information (spaces and pathways) to determine network technology and equipment selection. This is referred to as a___________design process
The type of apparatus housed in ERs vary greatly in size, purpose and function. Which two of the following active equipment is included? (Choose two.)
A company's marketing department Tails an internal compliance audit To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?
During the design phase, drawings for ICT communications spaces should be reviewed for Standards compliance and
You have just finished a design calling for 15 telecommunications outlets. You received word that the owner has increased his requirements by 40%. What size commercial DD (distribution device) is required to accommodate the increase?
During program execution, a program manager receives feedback from an executive sponsor (hat some program stakeholders may not understand the intended benefits of the program. Which will provide the greatest value to clarify stakeholder perceptions?
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?
A program stakeholder is concerned about information they receive about a project. Who is responsible for reviewing the communications management plan to assure adequate information is provided to the stakeholder'?
The project manager of project A develops a communications management plan. The project manager of project B is new and is uncertain how to develop appropriate communications for the company's staff
What should the program manager do to ensure communications on the component projects are consistent?
Communicating a project's design and technical specifications to the client and stakeholders is part of the ___________of the project.
Exhibit:
In this future marina layout, what would be the pre-cabling guideline to follow for the terminal A?
What is the RECOMMENDED bend radius of a conduit with an internal diameter of 51 mm (2 in)?