The group technique that enhances brainstorming with a voting process used to rank the most useful ideas for prioritization is called the:
Which of the following is a tool or technique used in the Acquire Project Team process?
Processes in the Planning Process Group are typically carried out during which part of the project life cycle?
The process improvement plan details the steps for analyzing processes to identify activities which enhance their:
A large portion of a projects budget is typically expended on the processes in which Process Group?
The iterative process of increasing the level of detail in a project management plan as greater amounts of information become available is known as:
The process of identifying and documenting relationships among the project activities is known as:
Which process numerically analyzes the effect of identified risks on overall project objectives?
A logical relationship in which a successor activity cannot start until a predecessor activity has finished is known as:
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
When a permitting agency takes longer than planned to issue a permit, this can be described as a risk:
Which Process Group contains the processes performed to complete the work defined in the project management plan to satisfy the project specifications?
The project management processes are usually presented as discrete processes with defined interfaces, while in practice they:
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating them into a comprehensive plan?
Which of the following is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen?
When a backward pass is calculated from a schedule constraint that is later than the early finish date that has been calculated during a forward pass calculation, this causes which type of total float?
A technique used to determine the cause and degree of difference between baseline and actual performance is:
Which risk management strategy seeks to eliminate the uncertainty associated with a particular upside risk by ensuring that the opportunity is realized?
Which tool or technique is used in the Develop Project Management Plan process?
An effective technique for resolving conflict that incorporates multiple viewpoints from differing perspectives to achieve consensus and commitment is:
Which quality tool may prove useful in understanding and estimating the cost of quality in a process?
Which process involves the creation of a document that provides the project manager with the authority to apply resources to a project?
A project team attempts to produce a deliverable and finds that they have neither the expertise nor the time to complete the deliverable in a timely manner. This issue could have been avoided if they had created and followed a:
The following chart contains information about the tasks in a project.
Based on the chart, what is the schedulevariance (SV) for Task 8?
Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:
Which basic quality tool explains a change in the dependent variable in relationship to a change observed in the corresponding independent variable?
Those who enter into a contractual agreement to provide services necessary for a project are:
A project requires a component with well-understood specifications. Performance targets are established at the outset, and the final contract price is determined after completion of all work based on the seller's performance. The most appropriate agreement with the supplier is:
Plan Communications Management develops an approach and plan for project communications based on stakeholders' needs and requirements and:
Which document in the project management plan can be updated in the Plan Procurement Management process?
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and relying on interpersonal skills to convince others to cooperate toward common goals?
The following is a network diagram for a project.
The critical path for the project is how many days in duration?
The risk response strategy in which the project team acts to reduce the probability of occurrence or impact of a risk is known as:
The following is a network diagram for a project.
What is the critical path for the project?
Which of the following is an input to the Direct and Manage Project Execution process?
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
Which technique helps to determine the risks that have the most potential impact on a project?
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
Which of the following Project Communication Management processes uses performance reports as an input?
What provides information regarding the ways people, teams, and organizational units behave?
Which cost estimate technique includes contingencies to account for cost uncertainty?
The project scope statement and resource calendars are inputs to which Project Time Management process?
In which process is a project manager identified and given the authority to apply resources to project activities?
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
Which of the following is a tool and technique used in the Develop Schedule process?
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
Which process is included in the Project Integration Management Knowledge Area?
Which of the following processes are part of the Project Integration Management Knowledge Area?
The project manager notes that stakeholders are aware of the project and potential impacts and are actively engaged in ensuring that the project is a success. The engagement level of the stakeholders should be classified as:
A project manager at a publishing company decides to initiate the editing phase of the project as soon as each chapter is written. Which type of Sequence Activities tool and technique is involved, considering that there was a start-to-start relationship with a 15-day delay?
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
Which input to Collect Requirements is used to identify stakeholders who can provide information on requirements?
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
The procurement process that documents agreements and related documentation for future reference is known as:
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
Change requests are an output from which Project Integration Management process?
A collection of projects managed as a group to achieve strategic objectives is referred to as a: