Answer the following questions about using facilitation of a workshop to co-
design organizational change.
When facilitating a workshop to design a process, which recommendation is MOST likely to create a good solution?
To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.
Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?
The Web Content Manager has provided the Web Developer with a mock up
of the 'Contact Us' page, to be created for the new coffee bar insurance
product. When producing the code, the Web Developer has created a button
that reads 'Delete' instead of 'Cancel'.
What action should the Web Content Manager take?
Which 2 statements represent appropriate entries for the Development
Approach Definition?
Answer the following questions about the contents of the DSDM
products.
Each of the following questions includes true statements about the project
but only two statements are appropriate entries for the DSDM product
identified.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 statements represent appropriate entries for the Business Case?
Which 2 actions should the Business Visionary take to implement the new
Must Have requirement?
Which 2 statements represent appropriate entries for the Prioritised
Requirements List?
Answer the following questions about the DSDM Lifecycle.
Decide if each observation is an appropriate application of Agile Project Management for
this project and select the option that supports your decision.
When the project was in the Feasibility phase it was initially proposed by the Finance
Manager that it was a fixed price for a fixed specification' project. The Project Manager
has decided that the best way to tackle it would be to leave the development of the least
valuable features of the product until last.
Is this an appropriate application of the DSDM lifecycle?
Xan Insurance Company operates from one location - a large, open-plan
office in the centre of a city. Those employees that will be working within the
Solution Development Team are all based in this office but work at different
ends of the office in separate departments.
What action should the Project Manager suggest to ensure the most effective
collaboration of the Solution Development Team?
Which 2 actions should the Team Leader take to implement the new Must
Have requirement?
Which 2 actions should the Technical Coordinator take to implement the new
Must Have requirement?
The Solution Development Team are progressing through the first Structured
Timebox.
What should the Project Manager do to lead the team at this time?
Column 1 is a list of individuals from within the Xan Insurance Company
and their key responsibility within the Web project.
For each individual in Column 1, select from Column 2 the Agile Project
Management team role they are fulfilling. Each selection from Column 2 can
be used once, more than once or not at all.
Column 1
Manager of Web & Digital
Media - will oversee and report
progress on the delivery of the
overall system.
Finance Director - has
budgetary control and will
release finance for the project
subject to expected benefits.
Sales Manager - will formulate
design options for new
business processes that do not
adversely affect business as
usual.
Operations Manager - oversees
the design and integrity of the
technical aspects of the
solution.
Column 2
Business Sponsor
Business Analyst
Business Ambassador
Business Advisor
Solution Developer
Technical Coordinator
DSDM Coach
Project Manager
Answer the following questions about actions to be taken by different
roles.
The Business Sponsor has decided that the new coffee shop insurance
product website pages will include the financial transaction functionality to
support the end-to-end sales process. The Business Sponsor views this as a
valuable sales tool, enabling customers to pay for insurance policies online. If
successful, this new financial transaction functionality is to be made available
across all other insurance products. This is a new Must Have requirement.
All parties are to be invited to a workshop to discuss the additional work
required to deliver the required solution including the new Must Have
requirement. The areas to be discussed include specialist skills required and
possible legal, financial and technical standards to be adhered to.
Remember to limit your answers to the number of selections requested in
each question.
Which 2 actions should the Business Sponsor take to implement the new Must
Have requirement?
The Marketing Director has insisted that detailed requirements for the new
coffee bar insurance web pages should be clearly defined in the early phases
of the project.
What action should the Project Manager take?
Which 2 actions should the Project Manager take to implement the new Must
Have requirement?
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.
Remember to limit your answers to the number of selections requested in each question.
Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?
Using the Project Scenario and the additional information provided for
this question in the Scenario Booklet, answer the following questions
about Feasibility.
Remember to limit your answers to the number of selections requested in each
question.
Which 2 statements describe the appropriate application of Agile Project
Management when developing the Delivery Plan?
The change management team is creating the change analytics strategy for the change programme.
Below is an extract of recipients, measures and source data that have been proposed.
Answer the following question about the sources of conflict in change
situations.
Column 1 is a list of statements about sources of conflict in change situations.
Column 2 contains the names of the eight sources of conflict identified by Art
Bell and Brett Hart. For each statement in Column 1, select from Column 2 the
source of conflict to which it MOST relates. Each selection from Column 2 can
be used once, more than once or not at all.
The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions.
Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.
The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director's leadership team in the UniCo building. At the last Operations' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.
Is this an appropriate approach to reward the brain in the need for 'status', and
why?
Which statement should be recorded under the High-level timing considerations heading?
Using the information provided in the additional information, answer the following question on building a change analytics strategy.
Do the measures to be monitored by the Sales Director represent appropriate measures for assessing change readiness?
The Customer Services Manager used to work in a call center, answering customer calls. Concerned for staff wellness, this manager has decided to invite anyone who is finding the changes overwhelming to contact them directly so that they can arrange appropriate support.
Which preference does this behavior BEST display?
As time goes by, there is an increase in Customer Services staff asking questions about how their skills development will be supported under the new structure and how they will influence decisions about the projects they will be assigned to work on.
Which is the MOST appropriate response from the Customer Service Director?
The Customer Services Director has announced the new structure at a large presentation for all Customer Services staff. The scale and design of the change have surprised many of the staff.
In the weeks immediately following the Customer Services Director’s initial presentation, there have been rumors of the Help Desk staff talking unhappily in small groups, with blame directed at "the management" for a recent period of poor performance of the department.
Which approach is the MOST appropriate way for the Customer Services Director to create early involvement in the change?
The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open
Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.
At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.
However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video
tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of
storage space on the company server and require minimal maintenance.
The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.
Remember to limit your answers to the number of selections requested in each question.
Which 2 individuals should the Facilitator invite to participate in the Workshop?
Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.
Column 1:
1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.
2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.
3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.
4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.
5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.
Column 2:
A) Thought
B) Action
C) Conversation
Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?
Answer the following questions about the use of the Agile principles.
Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional
wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.
Which Agile principle MOST influences this course of action?
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox
Plan for Timebox B?
Find out who is responsible for challenging the priority of requirements and deal with them accordingly.
Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the
responsibilities of the roles in the Agile team.
Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.
Each option can be used once, more than once or not at all.
Assertion
The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.
BECAUSE
The Project-level roles are responsible for directing, managing and co-
ordinating the project.
The Procurement Manager is an appropriate representative of the end user of the solution.
BECAUSE
The Business Ambassador should be empowered to make decisions within
the boundaries of their role, without referral to higher authorities outside
the Solution Development Team.
The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.
BECAUSE
Extra Solution Developers can provide a supporting role for a Lead
Developer.
The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.
BECAUSE
The Business Ambassador is responsible for ensuring that business needs
are properly analysed.
The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.
BECAUSE
The Business Visionary is responsible for promoting the business vision to
all interested parties.
Answer the following questions about the acceptance criteria within the project.
Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.
During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox A.
Is this an appropriate action related to acceptance criteria?
The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in
the gardens could be enjoyed.
Which Agile principle MOST influences this course of action?