AgilePM-Practitioner Sample Questions Answers

Questions 4

Answer the following questions about using facilitation of a workshop to co-

design organizational change.

When facilitating a workshop to design a process, which recommendation is MOST likely to create a good solution?

Options:

A.

The focus should be on immediate action to reduce the organizational costs.

B.

The workshop should be held off-site to create independent thought.

C.

The participants should cover all elements of the process and its implementation.

D.

Only the senior decision-makers should attend to ensure implementation is viable.

Buy Now
Questions 5

To ensure that the UniCo change programme is successful, the Chief Executive Officer (CEO) knows that correctly assigning the key change roles will be essential.

Which 2 statements BEST explain why the IT Support Manager is appropriate for the role of change agent for the change programme?

Options:

A.

Is good at quietly implementing directions without challenging decisions at every step.

B.

Is well-positioned to bring together other line leaders facing similar change situations.

C.

Has a strong network due to supporting all staff at all levels organization-wide.

D.

Has direct line authority over the staff who will be changing internal IT systems.

E.

Wants to gain experience in change management to improve future implementations of IT systems.

Buy Now
Questions 6

The Web Content Manager has provided the Web Developer with a mock up

of the 'Contact Us' page, to be created for the new coffee bar insurance

product. When producing the code, the Web Developer has created a button

that reads 'Delete' instead of 'Cancel'.

What action should the Web Content Manager take?

Options:

A.

Prepare a defence for when the problem is identified, ensuring the

responsibility is with the Web Developer.

B.

Hide the problem and hope that this detail can be changed at a later date.

C.

Raise an issue to the Project Manager when the solution is deployed.

D.

Discuss the issue with the Web Developer and decide what action is

required to change this detail.

Buy Now
Questions 7

Which 2 actions demonstrate connectivity?

Options:

A.

Arrange a number of briefing sessions for Customer Services staff, over lunch times and in a comfortable setting.

B.

Make short videos available showing how customer service teams from other companies effectively provide services for these types of offerings.

C.

Create a central area on the UniCo internal shared work system for the Change Programme to collaborate and comment on the materials.

D.

Ask the senior leadership to provide examples of other companies undertaking, and successfully overcoming, similar challenges.

E.

Send the plans of the new office layout to the Selco staff showing them where each individual will be located.

Buy Now
Questions 8

Which 2 statements represent appropriate entries for the Development

Approach Definition?

Options:

A.

The Sales Manager will introduce an awards or bonus scheme, designed

to create competition between the sales assistants.

B.

Once deployed, the number of policies sold through traditional telephone

sales will be compared with the number of sales processed online

through the website.

C.

An easy to use web development tool called 'WebMatrix' is to be used to

develop and maintain the website extension.

D.

The Finance Director has requested a detailed report be produced after

12 weeks, showing costs to date and forecast cost to complete.

E.

Accessibility and performance of the new online quotation area is to be

tested using a tool called Sitebeam.

Buy Now
Questions 9

Answer the following questions about the contents of the DSDM

products.

Each of the following questions includes true statements about the project

but only two statements are appropriate entries for the DSDM product

identified.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 statements represent appropriate entries for the Business Case?

Options:

A.

A list of high-level functional and non-functional requirements that the

project should meet written as User Stories.

B.

Coffee shops that sell Fairtrade products and alcohol from local breweries

out perform other coffee shops in the market.

C.

The Sales Manager has been asked to produce a report within the next

two days showing the number of generic insurance policies sold to coffee

shops over the past three years.

D.

The Sales Manager has calculated that the new coffee shop insurance

product will increase revenues by 10% each week.

E.

Market research shows that the number of coffee shop patrons taking

legal action against retailers has increased by 200% over the past two

years.

Buy Now
Questions 10

Which 2 actions should the Business Visionary take to implement the new

Must Have requirement?

Options:

A.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Ensure the marketing and sales teams are working together to deliver the

most effective outcome.

E.

Consolidate and circulate an agenda for the workshop.

Buy Now
Questions 11

Which 2 statements represent appropriate entries for the Prioritised

Requirements List?

Options:

A.

Creation of a new coffee shop insurance product on the existing website

is expected to increase the insurance company's revenues by up to 10%

per week.

B.

All correspondence sent to coffee shop owners by the new system should

contain the XAN logo in the top left hand corner of the page.

C.

Further website developments to allow existing customers to access

services online are NOT to be included within the scope of this project.

D.

The Business Visionary will provide a formal acceptance of the coffee

shop insurance product.

E.

An assessment will be made of the effectiveness of the techniques used

on the project, in line with the principles of Agile Project Management.

Buy Now
Questions 12

Answer the following questions about the DSDM Lifecycle.

Decide if each observation is an appropriate application of Agile Project Management for

this project and select the option that supports your decision.

When the project was in the Feasibility phase it was initially proposed by the Finance

Manager that it was a fixed price for a fixed specification' project. The Project Manager

has decided that the best way to tackle it would be to leave the development of the least

valuable features of the product until last.

Is this an appropriate application of the DSDM lifecycle?

Options:

A.

Yes, because the later parts of the project should reflect the least valuable features

of the product being built.

B.

Yes, because in a DSDM project there is no detailed specification upfront.

C.

No, because the Solution Development Team should decide which features are left

until last.

D.

No, because the most valuable features of the project should be delivered last.

Buy Now
Questions 13

Xan Insurance Company operates from one location - a large, open-plan

office in the centre of a city. Those employees that will be working within the

Solution Development Team are all based in this office but work at different

ends of the office in separate departments.

What action should the Project Manager suggest to ensure the most effective

collaboration of the Solution Development Team?

Options:

A.

Create an email group for the Solution Development Team to collaborate

on ideas.

B.

Set up a telephone or video conferencing facility so that all members of

the team can collaborate effectively.

C.

Relocate these employees to a new project area, with a number of desks

where the Solution Development Team can sit together.

D.

No action required as these employees are located in the same office.

Buy Now
Questions 14

Which 2 actions should the Team Leader take to implement the new Must

Have requirement?

Options:

A.

Consolidate and circulate an agenda for the workshop.

B.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

C.

Discuss the development interfaces and dependencies with the Solution

Development Team to ensure the associated Timebox is appropriate.

D.

Agree to de-scope Should Have and/or Could Have requirements to allow

for the new Must Have functionality.

E.

Source and hire a web developer with experience in developing online

financial transaction functionality.

Buy Now
Questions 15

Which 2 actions should the Technical Coordinator take to implement the new

Must Have requirement?

Options:

A.

Ensure that the latest version of the website design in the Solution

Architecture Definition is provided to all members of the Solution

Development Team.

B.

Assess the impact of the new Must Have requirement on the original

Business Case.

C.

Add the additional tasks required to create the financial transaction

functionality to the Timebox Plan.

D.

Consolidate and circulate an agenda for the workshop.

E.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

Buy Now
Questions 16

The Solution Development Team are progressing through the first Structured

Timebox.

What should the Project Manager do to lead the team at this time?

Options:

A.

Maintain a tight control on progress, recording all discussions and making

all decisions.

B.

The Project Manager should do nothing during a Timebox.

C.

Attend the Daily Stand-up and discuss any problems at the end.

D.

Update the Team Board with a summary of team progress and the current

status of work.

Buy Now
Questions 17

Column 1 is a list of individuals from within the Xan Insurance Company

and their key responsibility within the Web project.

For each individual in Column 1, select from Column 2 the Agile Project

Management team role they are fulfilling. Each selection from Column 2 can

be used once, more than once or not at all.

Column 1

Manager of Web & Digital

Media - will oversee and report

progress on the delivery of the

overall system.

Finance Director - has

budgetary control and will

release finance for the project

subject to expected benefits.

Sales Manager - will formulate

design options for new

business processes that do not

adversely affect business as

usual.

Operations Manager - oversees

the design and integrity of the

technical aspects of the

solution.

Column 2

    Business Sponsor

    Business Analyst

    Business Ambassador

    Business Advisor

    Solution Developer

    Technical Coordinator

    DSDM Coach

    Project Manager

Options:

Buy Now
Questions 18

Answer the following questions about actions to be taken by different

roles.

The Business Sponsor has decided that the new coffee shop insurance

product website pages will include the financial transaction functionality to

support the end-to-end sales process. The Business Sponsor views this as a

valuable sales tool, enabling customers to pay for insurance policies online. If

successful, this new financial transaction functionality is to be made available

across all other insurance products. This is a new Must Have requirement.

All parties are to be invited to a workshop to discuss the additional work

required to deliver the required solution including the new Must Have

requirement. The areas to be discussed include specialist skills required and

possible legal, financial and technical standards to be adhered to.

Remember to limit your answers to the number of selections requested in

each question.

Which 2 actions should the Business Sponsor take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Check the viability of the project, following the inclusion of the new Must

Have requirement.

C.

Source and hire a web developer with experience in developing online

financial transaction functionality.

D.

Send a company-wide communication to explain the implications of the

business change to all interested parties.

E.

Assess the impact of the new Must Have requirement on the original

Business Case.

Buy Now
Questions 19

The Marketing Director has insisted that detailed requirements for the new

coffee bar insurance web pages should be clearly defined in the early phases

of the project.

What action should the Project Manager take?

Options:

A.

Refuse to discuss any detailed requirements in the early phases.

B.

Agree to document the finite details of each requirement to ensure the

web developers can accurately estimate the effort required to fulfil them.

C.

Hold an early discussion to the level of detail necessary to establish a

shared understanding of what is required.

D.

Capture the Marketing Director's requirements in detail but leave the

input of others until later in the project.

Buy Now
Questions 20

Which 2 actions should the Project Manager take to implement the new Must

Have requirement?

Options:

A.

Check for any documented standards which need to be applied to the

development of online financial transaction functionality.

B.

Add the tasks required to develop the new financial transaction

functionality to the Delivery Plan.

C.

Update the Delivery Plan to show the new financial transaction

functionality as a deliverable.

D.

Source and hire a web developer with experience in developing online

financial transaction functionality.

E.

Consolidate and circulate an agenda for the workshop.

Buy Now
Questions 21

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following questions about Feasibility.

Remember to limit your answers to the number of selections requested in each question.

Which 2 statements describe the appropriate application of Agile Project Management when developing the Solution Architecture Definition (SAD)?

Options:

A.

Paper-based drawings are to be used for each option being considered for the building and gardens.

B.

The SAD must include a physically-built miniature model of the Hoy Hall building.

C.

The Architecture Angels' Marketing Director can request a SAD to illustrate the achievability of complex elements of the solution.

D.

The views of the 'Hoy for Hoy Hall' Action Group members are NOT relevant to the business decision made by Architecture Angels' Finance Director when approving the final option.

E.

The SAD should contain high-level costs for all elements of each solution option.

Buy Now
Questions 22

Using the Project Scenario and the additional information provided for

this question in the Scenario Booklet, answer the following questions

about Feasibility.

Remember to limit your answers to the number of selections requested in each

question.

Which 2 statements describe the appropriate application of Agile Project

Management when developing the Delivery Plan?

Options:

A.

The Project Manager should include any known constraints associated with planning permission.

B.

The Project Manager should NOT need to identify any risks this early in the project.

C.

The approach to the project should be based on the Project Approach Questionnaire responses.

D.

The Earth Excavations' Head Gardener should be excluded from discussions related to deliverables since contracts are NOT yet signed.

E.

The Architecture Angels' Marketing Director should be involved in the development of the Delivery Plan.

Buy Now
Questions 23

The change management team is creating the change analytics strategy for the change programme.

Below is an extract of recipients, measures and source data that have been proposed.

Answer the following question about the sources of conflict in change

situations.

Column 1 is a list of statements about sources of conflict in change situations.

Column 2 contains the names of the eight sources of conflict identified by Art

Bell and Brett Hart. For each statement in Column 1, select from Column 2 the

source of conflict to which it MOST relates. Each selection from Column 2 can

be used once, more than once or not at all.

Options:

Buy Now
Questions 24

The Change Manager is discussing the relocation of the Selco staff to the UniCo office with the Operations Director. They are using the SCARF framework of people's social experience to guide management actions.

Answer the following questions about the use of David Rock's SCARF framework to increase the motivation for change.

The founder of Selco, now the Applications Manager, is moving from an individual office to a desk in the shared area for the Operations Director's leadership team in the UniCo building. At the last Operations' group meeting, the Operations Director thanked the Applications Manager for cooperating fully with the relocation.

Is this an appropriate approach to reward the brain in the need for 'status', and

why?

Options:

A.

No, because 'status' should be rewarded by ensuring open, two-way

communication using rich channels.

B.

No, because the Application Manager's knowledge and skills are still

relevant and there no threat to 'status'.

C.

Yes, because highlighting cooperation provides an opportunity for the

Applications Manager to learn and develop.

D.

Yes, because praising people publicly helps to improve a person's

informal importance in the organization.

Buy Now
Questions 25

Which statement should be recorded under the High-level timing considerations heading?

Options:

A.

The traditional market has changed over the last year and UniCo can no longer rest on its previous success.

B.

UniCo lost significant market share in the last six months and faces ongoing increased competition in the next year.

C.

UniCo’s new finance system was delivered in the last quarter and training in the new system is almost complete.

D.

Completing the large contract with a Utilities company over the next nine months is a vital step to achieving the end vision.

Buy Now
Questions 26

Using the information provided in the additional information, answer the following question on building a change analytics strategy.

Do the measures to be monitored by the Sales Director represent appropriate measures for assessing change readiness?

Options:

A.

No, because change readiness measures should consist of mostly quantitative measures.

B.

No, because change readiness should be monitored using the change programme plan.

C.

Yes, because the Sales Director has identified measures that require new data sources.

D.

Yes, because these metrics provide opinions collected via mostly qualitative methods.

Buy Now
Questions 27

The Customer Services Manager used to work in a call center, answering customer calls. Concerned for staff wellness, this manager has decided to invite anyone who is finding the changes overwhelming to contact them directly so that they can arrange appropriate support.

Which preference does this behavior BEST display?

Options:

A.

Sensing.

B.

iNtuiting.

C.

Thinking.

D.

Feeling.

Buy Now
Questions 28

Which stakeholder should be placed within the 'primary' segment?

Options:

A.

Industry-related professional associations, whose strong opinions and judgments about industry trends reach wide audiences.

B.

The Utilities company, who selected UniCo to provide services but will dictate their specific requirements and operational terms.

C.

The Operations Director, who will consult with others to understand their requirements and decide on the approach.

D.

The UniCo investors, who have provided the finance to support the innovation and improvement needed to recover profitability.

Buy Now
Questions 29

As time goes by, there is an increase in Customer Services staff asking questions about how their skills development will be supported under the new structure and how they will influence decisions about the projects they will be assigned to work on.

Which is the MOST appropriate response from the Customer Service Director?

Options:

A.

Prepare presentations to all staff outlining the targets for the new structure.

B.

Support line leadership roles on how to include those asking the questions.

C.

Ask for the communications from the change teams to include the questions.

D.

Define the approach and governance for the Customer Services projects.

Buy Now
Questions 30

The Customer Services Director has announced the new structure at a large presentation for all Customer Services staff. The scale and design of the change have surprised many of the staff.

In the weeks immediately following the Customer Services Director’s initial presentation, there have been rumors of the Help Desk staff talking unhappily in small groups, with blame directed at "the management" for a recent period of poor performance of the department.

Which approach is the MOST appropriate way for the Customer Services Director to create early involvement in the change?

Options:

A.

Target those staff in the Help Desk who are change-averse so that they are the first ones involved in the program.

B.

Delay communications a few weeks so that all staff have time to think for themselves about the benefits of the new structure.

C.

Identify those staff who would be willing to trial new Help Desk processes and work on pilots in the department.

D.

Encourage the Help Desk staff to begin setting goals for themselves under the new structure.

Buy Now
Questions 31

The project is now in the second week of Timebox C. This is the final Timebox of Project Increment 1 and is scheduled to take one month. The plan is to open

Hoy Hall to the public at the end of this Increment. A Must Have requirement of Timebox C is the implementation of a hotel reservation system.

At the Daily Stand-up, the Software Developer working on the reservation system reported that the framework for the system is now complete and ready for content.

However, this work cannot progress further due to a disagreement over the content. The Marketing Director insists the system is to hold professional photos and video

tours of the facilities and grounds. These require a lot of storage space and regular updates. The IT Operations Manager insists the system is to take less than 5GB of

storage space on the company server and require minimal maintenance.

The Team Leader has arranged a Facilitated Workshop to discuss the content and agree the way forward.

Remember to limit your answers to the number of selections requested in each question.

Which 2 individuals should the Facilitator invite to participate in the Workshop?

Options:

A.

Chief Executive (Steering Group)

B.

Representative for Earth Excavations (Solution Developer)

C.

Representative for Timber Tigers (Solution Developer)

D.

IT Operations Manager (Solution Development Team)

E.

Marketing Director (Business Visionary)

Buy Now
Questions 32

Column 1 is a list of actions taken within the project. For each action in Column 1, select from Column 2 the iterative development activity that the action represents. Each selection from Column 2 can be used once, more than once or not at all.

Column 1:

1.The Solution Development Team cleared and prepared the area, ready for the bar infrastructure to be installed.

2.The Gardener decided the order in which the flowers would be planted in the borders and jotted it down in a notebook.

3.Before the Solution Development Team built the infrastructure for the bar area, the Architect pointed out what was required.

4.The Architect checked with the decorators that tasks had been completed to a satisfactory standard, and agreed a list of items that needed further coats of paint or cleaning up.

5.The Gardener began planting the borders and has placed an order for further bulbs to complete this task.

Column 2:

A) Thought

B) Action

C) Conversation

Options:

Buy Now
Questions 33

Which 2 statements describe the appropriate application of Agile Project Management when developing the Prioritised Requirements List during Feasibility?

Options:

A.

Details of which areas will require seeding in order to become lawn, and which are to become planted borders, should be captured.

B.

The re-laying of the driveway and a landscaping solution should be listed as Must Have requirements.

C.

The scope of the project should be agreed before moving into the Foundations phase.

D.

The responsibility for setting the priority of each of the requirements identified should be assigned to the Project Manager.

E.

Regulatory obligations associated with the redevelopment of Hoy Hall should be recorded as Must Have requirements.

Buy Now
Questions 34

Answer the following questions about the use of the Agile principles.

Final checks carried out on the rooms delivered in Timebox A show that two of the items do NOT meet the required Must Have standards related to the use of traditional

wall coverings and paints. These items have therefore been recognised as NOT delivered and will have to be re-planned.

Which Agile principle MOST influences this course of action?

Options:

A.

Collaborate.

B.

Never compromise quality.

C.

Build incrementally from firm foundations.

D.

Communicate continuously and clearly.

Buy Now
Questions 35

Which 2 individuals would be suitable for the role of Workshop Facilitator?

Options:

A.

Team Leader

B.

IT Operations Manager

C.

Marketing Director

D.

Software Developer

E.

Project Manager

Buy Now
Questions 36

Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox

Plan for Timebox B?

Options:

A.

Marketing Director, in the role of Business Visionary.

B.

Team Leader.

C.

Project Manager and Architect, in the role of Technical Co-ordinator.

D.

Architecture Angels' Senior Management Team.

Buy Now
Questions 37

Find out who is responsible for challenging the priority of requirements and deal with them accordingly.

Options:

A.

Ask the Team Leader to resolve the situation.

B.

Ask the Marketing Director to explain to the Solution Development Team why the windows are a Must Have priority.

C.

Remove empowerment from the Solution Development Team.

D.

What action should the Project Manager take when dealing with the Solution Development Team's argument that the windows should not be a Must Have priority?

Buy Now
Questions 38

Using the Project Scenario and the additional information provided for this question in the Scenario Booklet, answer the following question about the

responsibilities of the roles in the Agile team.

Lines 1 to 5 in the table below consist of an assertion statement and a reason statement. For each line identify the appropriate option, from options A to E, that applies.

Each option can be used once, more than once or not at all.

Assertion

    The Marketing Director, in the role of Business Visionary, is empowered to overrule cost restrictions advised by the Chief Accountant, who is appointed as Business Ambassador.

BECAUSE

The Project-level roles are responsible for directing, managing and co-

ordinating the project.

    The Procurement Manager is an appropriate representative of the end user of the solution.

BECAUSE

The Business Ambassador should be empowered to make decisions within

the boundaries of their role, without referral to higher authorities outside

the Solution Development Team.

    The other specialist gardening team members from Earth Excavations would be suitable as Solution Developers, assigned alongside the Head Landscape Gardener.

BECAUSE

Extra Solution Developers can provide a supporting role for a Lead

Developer.

    The 'Hoy for Hoy Hall' Action Group members should be assigned as Business Ambassadors.

BECAUSE

The Business Ambassador is responsible for ensuring that business needs

are properly analysed.

    The Project Manager should plan the communication needed between the Marketing Director, in the role of Business Visionary, and the 'Hoy for Hoy Hall' Action Group.

BECAUSE

The Business Visionary is responsible for promoting the business vision to

all interested parties.

Options:

Buy Now
Questions 39

Answer the following questions about the acceptance criteria within the project.

Decide whether the approach to setting and using acceptance criteria has been applied appropriately and select the response that supports your decision.

During Solution Development Timebox A, a new Health and Safety requirement arises: the front door is required to have wheelchair access. This is a legal requirement and is a Must Have before any staff or general public access can be allowed. The Solution Development Team will work with the Local Planning Authority Officer, the specialist who identified the requirement, to identify further acceptance criteria for Solution Development Timebox A.

Is this an appropriate action related to acceptance criteria?

Options:

A.

Yes, because the new requirement needs to be understood, built and delivered in this Timebox.

B.

Yes, because the Local Planning Authority Officer owns the justification for the new requirement.

C.

No, because this new requirement would NOT be included in the original Prioritised Requirements List and therefore does NOT need acceptance criteria to be defined.

D.

No, because the Business Visionary is responsible for defining acceptance criteria.

Buy Now
Questions 40

The Head Landscape Gardener liaised with several key stakeholders before changing the direction of the pathway around the grounds to ensure all of the new features in

the gardens could be enjoyed.

Which Agile principle MOST influences this course of action?

Options:

A.

Focus on the business need.

B.

Deliver on time.

C.

Collaborate.

D.

Never compromise quality.

Buy Now
Exam Code: AgilePM-Practitioner
Exam Name: Agile Project Management (AgilePM) Practitioner Exam
Last Update: Apr 10, 2025
Questions: 134